563 N 26TH ST 90049

Certificate Information: 563 N 26TH ST 90049

Application / Permit
19014-20000-04055
Plan Check / Job No.
B19VN12474
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING, ADD 21' 1" X 23' 5" 2-CAR GARAGE, ADD 4' 4" X 14' 7" TO FRONT AND ADD 64' 8" X 46' IRREGULAR-SHAPE TO REAR, ADD 61' 10" X 28' 11" 2ND STORY, ADD 8' X 9' & 8' X 13' 7" 1ST FLOOR PATIO COVERS AND ADD 15' X 5' 10" & 15' 4" X 12' 7" 2ND FLOOR PATIO COVERS TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED,
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Green Plans Picked Up 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 GURUNATH NESARAJAH
Corrections Issued 8/17/2019 GURUNATH NESARAJAH
Quality Review Completed 8/21/2019 OMID HEDAYAT
Building Plans Picked Up 8/22/2019 APPLICANT
Plan Check Approved 12/24/2019 GURUNATH NESARAJAH
Issued 7/28/2020 APPLICANT
CofO in Progress 4/18/2022 EVAN COOPER
CofO Issued 5/4/2022 DANIEL ORRANTE
Permit Finaled 5/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/6/2019 GUILLERMO PETRA
Green Code Cleared 11/20/2019 AARON COSTA
ZI Cleared 12/10/2019 JOE LUCKEY
Low Impact Development Cleared 12/12/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/12/2019 THOMAS LANG
Specific Plan Cleared 12/18/2019 PEDRO AYALA

Contact Information

Architect Brumer,, Aaron Jason; Lic. No.: C30005 10999 RIVERSIDE DRIVE SUITE 300      STUDIO CITY, CA 91602
Contractor L A Build Corp; Lic. No.: 893881-B 21022 VICTORY BLVD      WOODLAND HILLS, CA 91367
Engineer Mills,, Garrett Ward; Lic. No.: S5271 553 S OAK KNOLL AVE      PASADENA, CA 91101

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/4/2020 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/18/2020 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/23/2020 Approved MICHAEL PELHAM
Footing/Foundation/Slab 9/23/2020 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 10/13/2020 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/15/2020 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/15/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 10/15/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 10/15/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 12/4/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 12/16/2020 Approved EVAN COOPER
HVAC-Rough 12/22/2020 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 1/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 2/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 2/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 2/24/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Shower Pan 2/24/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 3/9/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/9/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/17/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 3/17/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 3/17/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 3/23/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 3/23/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 3/26/2021 Approved OGANES TARAKHCHYAN
Insulation 4/26/2021 Partial Approval JESUS RODRIGUEZ
Pre-Inspection 4/26/2021 Partial Inspection SHAVONNE ESPINOZA
Drywall Nailing 5/5/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/18/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/25/2021 Approved ADAM ESCOTO
Grounding or Bonding 8/18/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 10/7/2021 Partial Inspection OGANES TARAKHCHYAN
Service/Power Release 10/8/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 11/10/2021 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 11/10/2021 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 11/23/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/1/2021 Approved OGANES TARAKHCHYAN
Gas Test 12/6/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 12/6/2021 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 12/29/2021 Approved JOHNNY MIRANDA
HVAC-Final 12/29/2021 Approved JOHNNY MIRANDA
Enclosure/Fence 1/6/2022 Corrections Issued JOHNNY MIRANDA
Final 1/19/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 1/19/2022 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 1/19/2022 Approved OGANES TARAKHCHYAN
Final 1/24/2022 Corrections Issued OGANES TARAKHCHYAN
Final 4/12/2022 Corrections Issued OGANES TARAKHCHYAN
Final 4/18/2022 OK to Issue CofO EVAN COOPER