10515 W ALSKOG ST 91352

Certificate Information: 10515 W ALSKOG ST 91352

Application / Permit
19014-20000-04041
Plan Check / Job No.
B19VN12445
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (7'-0" x 21'-6") TO EXTEND (E) DINING ROOM/KITCHEN, ADD (12'-7" x 22'-4") AND (3'-1" x 9'-5") TO EXTEND (E) ENTRY, REFRAME (E) ROOF. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/8/2020
Issuing Office
Current Status
CofO Issued on 11/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/26/2019 APPLICANT
Assigned to Plan Check Engineer 8/6/2019 JENNIFER LEE
Corrections Issued 8/6/2019 JENNIFER LEE
Green Plans Picked Up 12/10/2019 APPLICANT
Quality Review Completed 12/27/2019 CHON CHIO KUO
Building Plans Picked Up 1/2/2020 APPLICANT
Applicant returned to address corrections 3/19/2020 TROY DEGUZMAN
Plan Check Approved 3/20/2020 TROY DEGUZMAN
Issued 8/8/2020 APPLICANT
CofO in Progress 9/21/2021 WILLIAM KUEHN
Permit Finaled 11/10/2021 MICHAEL SMITH
CofO Issued 11/10/2021 MICHAEL SMITH
Permit Finaled 11/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/26/2019 THOMAS LANG
Low Impact Development Cleared 11/26/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/26/2019 THOMAS LANG
Grading Pre-Inspection Cleared 11/27/2019 JENNIFER LEE
BHO/Hillside ordinance Cleared 1/23/2020 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 1/23/2020 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 1/23/2020 APEKSHYA BAJRACHARYA
Green Code Cleared 3/2/2020 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,
Engineer , ; Lic. No.: C89103 1010 RALEIGH ST.   #107    GLENDALE, CA 91205

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/18/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 8/26/2020 Corrections Issued BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Corrections Issued BEAU COLLINS
Shower Pan 10/29/2020 Approved BEAU COLLINS
Shower Pan 10/30/2020 Approved CRAIG VAUGHAN
Deputy Wood Construction 11/5/2020 Conditional Approval BEAU COLLINS
BUILDING-Rough-Frame 11/9/2020 Partial Inspection BEAU COLLINS
ELECTRICAL-Rough 11/9/2020 Approved BEAU COLLINS
Green Building Rough 11/9/2020 Partial Approval BEAU COLLINS
HVAC-Rough 11/9/2020 Conditional Approval BEAU COLLINS
PLUMBING-Rough 11/9/2020 Approved BEAU COLLINS
Insulation 11/12/2020 Approved JOHN HAYES
Interior/Exterior Lathing 11/16/2020 Partial Approval BEAU COLLINS
Sewer 11/24/2020 Approved BEAU COLLINS
Drywall Nailing 12/1/2020 Approved BEAU COLLINS
Green Building Rough 12/1/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 12/1/2020 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 12/4/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 8/11/2021 Approved WILLIAM KUEHN
Final 8/11/2021 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 8/11/2021 Approved WILLIAM KUEHN
Green Building Final 8/11/2021 Not Ready for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 8/11/2021 SGSOV Approved WILLIAM KUEHN
Service/Power Release 8/11/2021 Approved WILLIAM KUEHN
Smoke Detectors 8/11/2021 Approved WILLIAM KUEHN
ELECTRICAL-Final 9/20/2021 Approved WILLIAM KUEHN
Final 9/20/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 9/20/2021 Approved WILLIAM KUEHN
HVAC-Final 9/20/2021 Approved WILLIAM KUEHN
PLUMBING-Final 9/20/2021 Approved WILLIAM KUEHN