18800 W TULSA ST 91326
Certificate Information: 18800 W TULSA ST 91326
- Application / Permit
- 19014-20000-04040
- Plan Check / Job No.
- B19VN12444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1st and 2nd story addition to rear of (E) SFD.
- Permit Issued
- Issued on 2/20/2020
- Issuing Office
- Valley
- Current Status
- Issued on 1/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2019 | HELEN NGUYEN |
| Corrections Issued | 9/10/2019 | HELEN NGUYEN |
| Quality Review Completed | 9/28/2019 | YOUNG KIM |
| Building Plans Picked Up | 10/7/2019 | APPLICANT |
| Green Plans Picked Up | 10/21/2019 | APPLICANT |
| Plan Check Approved | 12/20/2019 | HELEN NGUYEN |
| Issued | 2/20/2020 | LADBS |
| CofO in Progress | 8/26/2020 | JOHN JANSON |
| No Progress | 1/8/2025 | HENRY KIM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/3/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/3/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 12/17/2019 | MICHAEL AYERS |
Contact Information
| Contractor | Hanson David Walter; Lic. No.: 536128-B | P O BOX 280376 NORTHRIDGE, CA 91328 |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 1561 RUGBY CIR THOUSAND OAKS, CA 91360 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/20/2020 | Partial Approval | JOSEPH SAGEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | DONALD SUNSERI |
| Footing/Foundation/Slab | 5/22/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 6/8/2020 | Partial Approval | DONALD SUNSERI |
| ELECTRICAL-Rough | 6/8/2020 | Approved | DONALD SUNSERI |
| Green Building Rough | 6/8/2020 | Not Ready for Inspection | DONALD SUNSERI |
| HVAC-Rough | 6/8/2020 | Approved | DONALD SUNSERI |
| BUILDING-Rough-Frame | 6/16/2020 | Approved | JEFFREY PARD |
| Green Building Rough | 6/16/2020 | Approved | JEFFREY PARD |
| Insulation | 6/16/2020 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/16/2020 | Approved | JEFFREY PARD |
| Drywall Nailing | 6/23/2020 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 8/25/2020 | Approved | JEFFREY PARD |
| Final | 8/25/2020 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 8/25/2020 | Approved | JEFFREY PARD |
| HVAC-Final | 8/25/2020 | Approved | JEFFREY PARD |
| PLUMBING-Final | 8/25/2020 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 8/25/2020 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 8/25/2020 | Approved | JEFFREY PARD |