20358 W GILMORE ST 91306

Certificate Information: 20358 W GILMORE ST 91306

Application / Permit
19014-20000-04018
Plan Check / Job No.
B19VN12393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-0" X 20'-0" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 11/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 JEROME MAGAT PALMA
Corrections Issued 7/26/2019 JEROME MAGAT PALMA
Building Plans Picked Up 8/13/2019 APPLICANT
Plan Check Approved 11/1/2019 JEFFREY TANGONAN
No Progress 11/1/2019 JEROME MAGAT PALMA
Plan Check Approved 11/1/2019 JEROME MAGAT PALMA
Issued 11/21/2019 LADBS
CofO in Progress 12/10/2021 STEVEN BACK
Permit Finaled 12/13/2021 JOHN JANSON
CofO Issued 12/13/2021 JOHN JANSON
Permit Finaled 12/13/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 8/13/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/5/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 9/5/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 9/5/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 10/24/2019 RIDWAN HARDY
ZI Cleared 11/7/2019 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2020 Approved HENRY KIM
PLUMBING-Rough 3/13/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 3/25/2020 Partial Approval HENRY KIM
Sewer 3/25/2020 Approved HENRY KIM
Underground Mechanical 3/25/2020 Approved HENRY KIM
Excavation/Setback/Form/Re-Bar 4/2/2020 Approved HENRY KIM
BUILDING-Rough-Frame 6/5/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Corrections Issued HENRY KIM
HVAC-Rough 6/5/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 6/5/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 6/22/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval HENRY KIM
Green Building Rough 6/22/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 9/15/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval HENRY KIM
PLUMBING-Rough 9/15/2020 Corrections Issued HENRY KIM
Pre-Inspection 9/15/2020 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 10/8/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 10/8/2020 Approved HENRY KIM
Gas Test 10/8/2020 Partial Approval HENRY KIM
Green Building Rough 10/8/2020 Approved HENRY KIM
HVAC-Rough 10/8/2020 Approved HENRY KIM
Insulation 10/8/2020 Partial Approval HENRY KIM
Interior/Exterior Lathing 10/8/2020 Approved HENRY KIM
PLUMBING-Rough 10/8/2020 Approved HENRY KIM
Shower Pan 10/8/2020 Approved HENRY KIM
HVAC-Final 10/16/2020 Corrections Issued HENRY KIM
Insulation 10/16/2020 Approved HENRY KIM
Interior/Exterior Lathing 10/16/2020 Approved HENRY KIM
Drywall Nailing 10/22/2020 Approved HENRY KIM
Underground Mechanical 10/22/2020 Approved HENRY KIM
ELECTRICAL-Final 12/1/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 12/18/2020 Approved HENRY KIM
Final 12/18/2020 Corrections Issued HENRY KIM
Footing/Foundation/Slab 12/18/2020 Approved HENRY KIM
Gas Test 12/18/2020 Corrections Issued HENRY KIM
Green Building Final 12/18/2020 Approved HENRY KIM
HVAC-Final 12/18/2020 Corrections Issued HENRY KIM
PLUMBING-Final 12/18/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Not Ready HENRY KIM
Smoke Detectors 12/18/2020 Approved HENRY KIM
Final 11/29/2021 Not Ready for Inspection STEVEN BACK
Gas Test 11/29/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 11/29/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 11/29/2021 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Not Ready STEVEN BACK
Final 12/10/2021 OK to Issue CofO STEVEN BACK
Gas Test 12/10/2021 Approved STEVEN BACK
HVAC-Final 12/10/2021 Approved STEVEN BACK
PLUMBING-Final 12/10/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/10/2021 SGSOV Approved STEVEN BACK
Service/Power Release 12/10/2021 Approved STEVEN BACK