6046 N RHODES AVE 91606
Certificate Information: 6046 N RHODES AVE 91606
- Application / Permit
- 19014-20000-04013
- Plan Check / Job No.
- B19VN12366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel kitchen, convert attached trellis to solid roof patio cover, add 2'10" x 10'3" and irregular shape 8.5' x 34'7" to bathroom/closet expansion and new laundry room per design
- Permit Issued
- Issued on 9/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | ALDOUS CHIC |
| Corrections Issued | 7/25/2019 | ALDOUS CHIC |
| Plan Check Approved | 7/25/2019 | SARKIS HARABEDIAN |
| Issued | 9/23/2019 | LADBS |
| CofO in Progress | 3/18/2021 | BRENDAN LOONEY |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
| CofO Issued | 12/25/2021 | MICHAEL SMITH |
| Permit Finaled | 12/25/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2019 | JULIUS GARCIA |
| Roof/Waste drainage to street | Cleared | 7/25/2019 | JULIUS GARCIA |
Contact Information
| Architect | Salcedo,, Glen Charles; Lic. No.: C33143 | P O BOX 14202 VAN NUYS, CA 91409 |
| Contractor | Moran'S Construction; Lic. No.: 1020402-B | 3624 MIDVALE AVE APT 4 LOS ANGELES, CA 90034 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/10/2019 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 10/10/2019 | Partial Approval | GREG ALLTON |
| PLUMBING-Rough | 10/25/2019 | Approved | ROBERT MINASSIANS |
| Drywall Nailing | 10/29/2019 | Partial Approval | GREG ALLTON |
| Green Building Rough | 10/29/2019 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 2/13/2020 | Approved | GREG ALLTON |
| Drywall Nailing | 2/13/2020 | Approved | GREG ALLTON |
| Final | 2/13/2020 | Partial Inspection | GREG ALLTON |
| Footing/Foundation/Slab | 2/13/2020 | Not Ready for Inspection | GREG ALLTON |
| Green Building Final | 2/13/2020 | Approved | GREG ALLTON |
| SGSOV-Seismic Gas S/O Valve | 2/13/2020 | SGSOV Approved | GREG ALLTON |
| Smoke Detectors | 2/13/2020 | Approved | GREG ALLTON |
| Service/Power Release | 2/18/2020 | Not Ready for Inspection | TROY SANDERS |
| Final | 2/25/2020 | Not Ready for Inspection | GREG ALLTON |
| Footing/Foundation/Slab | 2/25/2020 | Not Ready for Inspection | GREG ALLTON |
| Deputy Drilled-In Anchors | 10/1/2020 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/2/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/15/2020 | Approved | BRENDAN LOONEY |
| Wood Frame | 11/18/2020 | Partial Approval | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 12/23/2020 | Conditional Approval | BRENDAN LOONEY |
| Deputy Wood Construction | 12/23/2020 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2020 | Approved | DANIEL DREW |
| Rough-Elec/Plmb/HVAC | 12/31/2020 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 1/7/2021 | Conditional Approval | BRENDAN LOONEY |
| Drywall Nailing | 1/13/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/19/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 3/16/2021 | Approved | BRENDAN LOONEY |
| Final | 3/16/2021 | OK to Issue CofO | BRENDAN LOONEY |