7347 N RIVERTON AVE 91352

Certificate Information: 7347 N RIVERTON AVE 91352

Application / Permit
19014-20000-03865
Plan Check / Job No.
B19VN11896
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15' X 21'-0" IRREGULAR SHAPED TO AND CONVERT (E) 20'-0" X 20'-0" DETACHED GARAGE FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 8/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 JENNIFER LEE
Corrections Issued 7/24/2019 JENNIFER LEE
Applicant returned to address corrections 7/31/2019 RARES BODEA
Plan Check Approved 8/5/2019 RARES BODEA
Issued 8/6/2019 LADBS
CofO in Progress 10/23/2020 DANIEL DREW
CofO Issued 11/29/2021 MICHAEL SMITH
Permit Finaled 11/29/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/5/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/5/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/5/2019 LEE GUILBEAUX
Sewer availability Cleared 8/5/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/5/2019 LEE GUILBEAUX

Contact Information

No Data Available.

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2020 Approved RAYMOND KEHOE
Pre-Inspection 4/14/2020 No Access for Inspection TROY SANDERS
Pre-Inspection 4/16/2020 Partial Inspection BEAU COLLINS
Sewer 7/29/2020 Approved RAYMOND KEHOE
Underground Mechanical 7/29/2020 Approved RAYMOND KEHOE
Drywall Nailing 10/13/2020 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/13/2020 SGSOV Not Ready DANIEL DREW
ELECTRICAL-Final 10/14/2020 Corrections Issued DANIEL DREW
HVAC-Final 10/14/2020 Corrections Issued DANIEL DREW
PLUMBING-Final 10/14/2020 Approved DANIEL DREW
Pre-Inspection 10/14/2020 Not Ready for Inspection DANIEL DREW
BUILDING-Rough-Frame 10/23/2020 Approved DANIEL DREW
Drywall Nailing 10/23/2020 Approved DANIEL DREW
ELECTRICAL-Final 10/23/2020 Approved DANIEL DREW
Final 10/23/2020 OK to Issue CofO DANIEL DREW
Footing/Foundation/Slab 10/23/2020 Approved DANIEL DREW
Green Building Final 10/23/2020 Approved DANIEL DREW
Green Building Rough 10/23/2020 Approved DANIEL DREW
HVAC-Final 10/23/2020 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Approved DANIEL DREW
Smoke Detectors 10/23/2020 Approved DANIEL DREW