11223 W COHASSET ST 91352

Certificate Information: 11223 W COHASSET ST 91352

Application / Permit
19014-20000-03864
Plan Check / Job No.
B19VN11895
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
30'-4" X 20'-1" ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. COMPLY WITH DEPARTMENT ORDER effective date 11/12/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 8/15/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 JEROME MAGAT PALMA
Corrections Issued 7/19/2019 JEROME MAGAT PALMA
Building Plans Picked Up 7/23/2019 APPLICANT
Plan Check Approved 8/9/2019 JEROME MAGAT PALMA
Issued 8/15/2019 LADBS
CofO in Progress 6/24/2022 JOHN HAYES
CofO Issued 8/1/2022 DANIEL ORRANTE
Permit Finaled 8/1/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/9/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/9/2019 GUILLERMO PETRA
Low Impact Development Cleared 8/9/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 8/9/2019 GUILLERMO PETRA
Sewer availability Cleared 8/9/2019 GUILLERMO PETRA
Hold Cleared 3/6/2020 LOURDES RAMIRO

Contact Information

No Data Available.

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/10/2020 Approved RAYMOND KEHOE
Footing/Foundation/Slab 3/20/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Approved TROY SANDERS
ELECTRICAL-Rough 5/26/2020 Not Ready for Inspection BEAU COLLINS
Rough-Elec/Plmb/HVAC 5/26/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 6/2/2020 Not Ready for Inspection BEAU COLLINS
PLUMBING-Rough 6/2/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 6/23/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 6/23/2020 Approved RAYMOND KEHOE
Green Building Rough 6/23/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 6/23/2020 Partial Approval RAYMOND KEHOE
PLUMBING-Rough 6/23/2020 Approved RAYMOND KEHOE
Insulation 7/16/2020 Approved RAYMOND KEHOE
Final 5/6/2021 Corrections Issued DANIEL DREW
Green Building Final 5/6/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 5/6/2021 Approved DANIEL DREW
Final 7/29/2021 Corrections Issued DANIEL DREW
Final 1/10/2022 Corrections Issued THOMAS FINNILA
Final 1/27/2022 No Access for Inspection DAVID MATSON
ELECTRICAL-Final 2/1/2022 Approved MICHEL ABAJAN
Final 2/1/2022 Corrections Issued MICHEL ABAJAN
HVAC-Final 2/1/2022 Approved MICHEL ABAJAN
PLUMBING-Final 2/1/2022 Approved MICHEL ABAJAN
Final 3/30/2022 Corrections Issued ARAM AVEDISIAN
Final 5/12/2022 Not Ready for Inspection MISAEL ESPARZA
Final 6/8/2022 Corrections Issued MISAEL ESPARZA
Final 6/23/2022 OK to Issue CofO JOHN HAYES