1227 W 51ST ST 90037

Certificate Information: 1227 W 51ST ST 90037

Application / Permit
19014-20000-03823
Plan Check / Job No.
B19VN11809
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-0" X 24'-4" ADDITION TO (E) SINGLE FAMILY DWELLING FOR (2) NEW BEDROOMS. INTERIOR REMODEL TO CONVERT (E) LAUNDRY ROOM TO BATHROOM AND FOR (1) NEW BATHROOM AT LIVING ROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2019 APPLICANT
Assigned to Plan Check Engineer 7/17/2019 BINH PHAN
Corrections Issued 7/17/2019 BINH PHAN
Plan Check Approved 2/5/2020 ROSENDO MEDINA
Issued 2/5/2020 LADBS
CofO in Progress 8/6/2020 ROBERT MCDOWELL
Permit Finaled 3/18/2021 DEROLD HAUFF
CofO Issued 3/18/2021 DEROLD HAUFF
Permit Finaled 3/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/17/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/17/2019 MARKOS PEREZ-BRAN
ZI Cleared 2/4/2020 HELEN JADALI
Roof/Waste drainage to street Cleared 2/5/2020 APEKSHYA BAJRACHARYA

Contact Information

Contractor Green Movement Construction Inc; Lic. No.: 1062285-B 21031 WARNER CENTER LANE   B    WOODLAND HILLS, CA 91367

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/12/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 3/12/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/19/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/25/2020 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 4/3/2020 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Rough 4/3/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 4/3/2020 Not Ready for Inspection ENRIQUE MIRELES
HVAC-Rough 4/3/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 4/3/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 4/15/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 4/15/2020 Approved COREY HUPP
Green Building Rough 4/15/2020 Not Ready for Inspection COREY HUPP
Insulation 4/21/2020 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 4/22/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 4/22/2020 Approved ROBERT MCDOWELL
Green Building Rough 4/22/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 4/22/2020 Approved ROBERT MCDOWELL
Drywall Nailing 4/30/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 4/30/2020 Approved SABAS ALONSO
ELECTRICAL-Final 8/6/2020 Approved ROBERT MCDOWELL
Final 8/6/2020 OK to Issue CofO ROBERT MCDOWELL
Green Building Final 8/6/2020 Approved ROBERT MCDOWELL
HVAC-Final 8/6/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 8/6/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 8/6/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 8/6/2020 Approved ROBERT MCDOWELL