4218 N WOODCLIFF ROAD 91403

Certificate Information: 4218 N WOODCLIFF ROAD 91403

Application / Permit
19014-20000-03815
Plan Check / Job No.
B19VN11775
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (10'-6"x 13'-0") & CONVERT (E) DETACHED STORAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER LA STD WFPP.
Permit Issued
Issued on 9/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 7/16/2019 TROY DEGUZMAN
Corrections Issued 7/16/2019 TROY DEGUZMAN
Building Plans Picked Up 8/12/2019 APPLICANT
Plan Check Approved 9/9/2019 TROY DEGUZMAN
Issued 9/9/2019 LADBS
CofO in Progress 12/1/2020 CHARLES POWELL
Permit Finaled 12/1/2020 MICHAEL SMITH
CofO Issued 12/1/2020 MICHAEL SMITH
Permit Finaled 12/1/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 8/23/2019 APEKSHYA BAJRACHARYA
Grading Pre-Inspection Cleared 9/9/2019 TROY DEGUZMAN

Contact Information

Contractor Cali Builders & Construction Inc; Lic. No.: 1051566-B 6924 VESPER AVE APT 111      VAN NUYS, CA 91405

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/2/2019 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 10/30/2019 No Access for Inspection JEFFREY PARD
Footing/Foundation/Slab 10/30/2019 No Access for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 11/7/2019 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 11/7/2019 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 11/13/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/13/2019 Corrections Issued CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 11/15/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/15/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 11/15/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 11/18/2019 Conditional Approval CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 11/19/2019 Approved HENRY KIM
Excavation/Setback/Form/Re-Bar 11/19/2019 No Access for Inspection DANIEL ORRANTE
Footing/Foundation/Slab 11/20/2019 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/27/2019 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 11/27/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 11/27/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/11/2019 Approved CHRISTOPHE COCHRAN
Underground Mechanical 12/11/2019 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 12/13/2019 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 12/13/2019 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 12/18/2019 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/20/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 12/20/2019 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/20/2019 Partial Approval CHRISTOPHE COCHRAN
MERV13>=Rough 12/20/2019 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/31/2019 Approved CHRISTOPHE COCHRAN
Shower Pan 1/6/2020 Approved CHRISTOPHE COCHRAN
Insulation 1/7/2020 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/7/2020 Approved CHRISTOPHE COCHRAN
Shower Pan 1/7/2020 Approved CHRISTOPHE COCHRAN
Drywall Nailing 1/13/2020 Approved CHRISTOPHE COCHRAN
Sewer 4/29/2020 Partial Approval MISAEL ESPARZA
Underground Mechanical 4/29/2020 Partial Approval MISAEL ESPARZA
Sewer 6/4/2020 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 6/4/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 8/21/2020 Approved CHARLES POWELL
PLUMBING-Final 8/21/2020 Not Ready for Inspection CHARLES POWELL
Sewer 8/21/2020 Not Ready for Inspection CHARLES POWELL
Underground Mechanical 8/21/2020 Partial Approval CHARLES POWELL
Sewer 8/25/2020 Approved CHARLES POWELL
Underground Mechanical 8/25/2020 Approved CHARLES POWELL
Final 11/16/2020 Partial Approval CHARLES POWELL
Green Building Final 11/16/2020 Approved CHARLES POWELL
MERV13>=Final 11/16/2020 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved CHARLES POWELL
Smoke Detectors 11/16/2020 Approved CHARLES POWELL