710-712 W 149TH ST 90247

Certificate Information: 710-712 W 149TH ST 90247

Application / Permit
19014-20000-03812
Plan Check / Job No.
B19VN11770
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove attached enclosed patio cover, convert attached garage to accessory dwelling unit per AB494 & SB229 with irregular shape 14'8" x 31'10" addition. All works are per WFPP
Permit Issued
Issued on 8/5/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 7/16/2019 ALDOUS CHIC
Corrections Issued 7/17/2019 ALDOUS CHIC
Building Plans Picked Up 7/19/2019 APPLICANT
Plan Check Approved 7/31/2019 ALDOUS CHIC
Issued 8/5/2019 LADBS
CofO in Progress 9/30/2020 EUGENE CASSIDY
Permit Finaled 10/15/2020 DEROLD HAUFF
CofO Issued 10/15/2020 DEROLD HAUFF
Permit Finaled 10/15/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/24/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/24/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/24/2019 LEE GUILBEAUX
Sewer availability Cleared 7/24/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/23/2020 Corrections Issued JOHN KLARIN
METHANE-Barrier 1/23/2020 Approved JOHN KLARIN
METHANE-Subgrade 1/23/2020 Approved JOHN KLARIN
PLUMBING-Rough 1/23/2020 Approved JOHN KLARIN
Footing/Foundation/Slab 2/3/2020 Corrections Issued WILLIAM ROSE
Footing/Foundation/Slab 2/12/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 4/28/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Approved BRIAN CHRISTIAN
Green Building Rough 4/28/2020 Approved BRIAN CHRISTIAN
MERV13>=Rough 4/28/2020 Approved BRIAN CHRISTIAN
METHANE-Rough 4/28/2020 Approved BRIAN CHRISTIAN
PLUMBING-Rough 4/28/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 5/6/2020 Conditional Approval BRIAN CHRISTIAN
Green Building Rough 5/6/2020 Corrections Issued BRIAN CHRISTIAN
Interior/Exterior Lathing 5/6/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 5/11/2020 Approved BRIAN CHRISTIAN
Green Building Rough 5/11/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 5/11/2020 Approved BRIAN CHRISTIAN
Insulation 5/11/2020 Approved BRIAN CHRISTIAN
Shower Pan 5/11/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/15/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/15/2020 Approved BRIAN CHRISTIAN
Final 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 7/2/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/2/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 7/2/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/17/2020 SGSOV Not Ready EUGENE CASSIDY
Final 7/22/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/22/2020 Approved EUGENE CASSIDY
Green Building Final 7/22/2020 Approved EUGENE CASSIDY
MERV13>=Final 7/22/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/22/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/22/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/28/2020 Approved EUGENE CASSIDY
Final 7/28/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 7/28/2020 Approved EUGENE CASSIDY
PLUMBING-Final 7/28/2020 Approved EUGENE CASSIDY
Service/Power Release 7/28/2020 Approved EUGENE CASSIDY