2107-2109 N REDROCK CT 90039
Certificate Information: 2107-2109 N REDROCK CT 90039
- Application / Permit
- 19014-20000-03630
- Plan Check / Job No.
- B19VN11231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION OF (158 SF) AND REMODEL ON PILES TO (E) SINGLE FAMILY DWELLING, CONVERT (E) PORTION OF SPACE OF SINGLE FAMILY DWELLING TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 10/23/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2019 | APPLICANT |
| Green Plans Picked Up | 7/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2019 | TROY DEGUZMAN |
| Corrections Issued | 7/29/2019 | TROY DEGUZMAN |
| Quality Review Completed | 8/6/2019 | STEVEN KIM |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Applicant returned to address corrections | 9/27/2019 | TROY DEGUZMAN |
| Plan Check Approved | 10/8/2019 | TROY DEGUZMAN |
| Issued | 10/23/2019 | LADBS |
| CofO in Progress | 2/16/2022 | JOSEPH MCGARRY |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
| CofO Issued | 2/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Green Code | Cleared | 9/12/2019 | AARON COSTA |
| Address approval | Cleared | 9/13/2019 | ADRIAN CASTRO |
| Address approval | Cleared | 9/13/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/13/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/13/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/27/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 9/27/2019 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 9/27/2019 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 9/27/2019 | TROY DEGUZMAN |
Contact Information
| Architect | Bullock,, Rachel Lane; Lic. No.: C35963 | 741 N OCCIDENTAL BLVD LOS ANGELES, CA 90026 |
| Contractor | Rockwood Development Group Inc; Lic. No.: 1019098-B | 4470 W SUNSET BLVD #407 LOS ANGELES, CA 90027 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/27/2020 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 1/28/2020 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/31/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 2/4/2020 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2020 | Partial Inspection | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/25/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 8/25/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 9/3/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 9/3/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 9/3/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/3/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/15/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 9/15/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 9/15/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/15/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/25/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/25/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Approved | JOSEPH MCGARRY |
| Gas Test | 9/25/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 9/25/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/25/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 9/25/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/25/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/25/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/19/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 10/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 10/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 10/19/2020 | Approved | JOSEPH MCGARRY |
| Insulation | 11/5/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 11/5/2020 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 12/8/2020 | Approved | JOSEPH MCGARRY |
| Gas Test | 12/8/2020 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 12/8/2020 | Approved | JOSEPH MCGARRY |
| Final | 8/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/20/2021 | Approved | JOSEPH MCGARRY |
| Green Building Final | 8/20/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 8/20/2021 | Approved | JOSEPH MCGARRY |
| Final | 1/7/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 1/7/2022 | Approved | JOSEPH MCGARRY |
| Final | 2/10/2022 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 2/16/2022 | Approved | JOSEPH MCGARRY |
| Final | 2/16/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| HVAC-Final | 2/16/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Final | 2/16/2022 | Approved | JOSEPH MCGARRY |