11228 W PICKFORD ST 90064

Certificate Information: 11228 W PICKFORD ST 90064

Application / Permit
19014-20000-03600
Plan Check / Job No.
B19VN11116
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-0" X 20'-0" IRREGULAR ADDITION TO (E) 2-CAR GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER SB229 AND AB494
Permit Issued
Issued on 9/9/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2019 APPLICANT
Assigned to Plan Check Engineer 7/5/2019 ROSENDO MEDINA
Corrections Issued 7/9/2019 ROSENDO MEDINA
Building Plans Picked Up 8/2/2019 APPLICANT
Applicant returned to address corrections 9/3/2019 ROSENDO MEDINA
Plan Check Approved 9/4/2019 ROSENDO MEDINA
Issued 9/9/2019 LADBS
CofO in Progress 7/1/2021 JUAN VALENZUELA
Permit Finaled 7/6/2021 KENNETH NAGLE
CofO Issued 7/6/2021 KENNETH NAGLE
Permit Finaled 7/6/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 8/5/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 8/5/2019 GUILLERMO PETRA
Sewer availability Cleared 8/5/2019 GUILLERMO PETRA
Low Impact Development Cleared 8/19/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 8/19/2019 CHRISTINE REUSCH
GPI Written Notices Cleared 9/3/2019 ROSENDO MEDINA
Grading Pre-Inspection Cleared 9/3/2019 ROSENDO MEDINA

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/13/2019 Partial Approval OGANES TARAKHCHYAN
Wood Frame 4/15/2020 Partial Approval OGANES TARAKHCHYAN
Wood Frame 4/20/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 5/8/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/2/2020 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 6/2/2020 Approved KEVIN SARGSYAN
Green Building Rough 6/2/2020 Not Ready for Inspection KEVIN SARGSYAN
MERV13>=Rough 6/2/2020 Approved KEVIN SARGSYAN
METHANE-Rough 6/2/2020 Not Ready for Inspection KEVIN SARGSYAN
Underground Mechanical 6/2/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 6/29/2020 Partial Approval JUSTIN CURTIS
Green Building Rough 6/29/2020 Approved JUSTIN CURTIS
METHANE-Rough 6/29/2020 Not Ready for Inspection JUSTIN CURTIS
Shower Pan 6/29/2020 Approved JUSTIN CURTIS
Insulation 7/6/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/14/2020 Approved JUSTIN CURTIS
ELECTRICAL-Rough 12/3/2020 Approved RICHARD ROBLES
Final 12/3/2020 Corrections Issued RICHARD ROBLES
Gas Test 12/3/2020 Approved RICHARD ROBLES
ELECTRICAL-Final 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Service/Power Release 12/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 1/4/2021 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Final 1/21/2021 Not Ready for Inspection KENNETH NAGLE
Service/Power Release 1/25/2021 Approved KENNETH NAGLE
Service/Power Release 2/10/2021 Approved KENNETH NAGLE
ELECTRICAL-Final 2/24/2021 Approved RICHARD ROBLES
BUILDING-Rough-Frame 4/9/2021 Approved EVAN COOPER
Final 4/9/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 4/9/2021 Approved EVAN COOPER
Green Building Final 4/9/2021 Approved EVAN COOPER
MERV13>=Final 4/9/2021 Approved EVAN COOPER
METHANE-Barrier 4/9/2021 Approved EVAN COOPER
METHANE-Final 4/9/2021 Approved EVAN COOPER
METHANE-Rough 4/9/2021 Approved EVAN COOPER
METHANE-Subgrade 4/9/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 4/9/2021 Approved EVAN COOPER
Final 6/29/2021 OK to Issue CofO JUAN VALENZUELA