20213 W MOBILE ST 91306

Certificate Information: 20213 W MOBILE ST 91306

Application / Permit
19014-20000-03560
Plan Check / Job No.
B19VN11023
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) 20.10' X 20.16' DETACHED TWO-CAR GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AND ADD A (N) 5' X 12'-9" TRELLIS, ALL WORK PER ENGINEERING
Permit Issued
Issued on 9/20/2021
Issuing Office
Current Status
CofO Corrected on 11/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 ANGELICA DAVE
Corrections Issued 7/3/2019 ANGELICA DAVE
Applicant returned to address corrections 7/24/2019 ANGELICA DAVE
Plan Check Approved 8/7/2019 RARES BODEA
Issued 9/20/2021 APPLICANT
CofO in Progress 11/22/2022 STEVEN BACK
CofO Issued-Status Void 11/29/2022 JOHN JANSON
Permit Finaled-Status Void 11/29/2022 JOHN JANSON
Re-Activate Permit 11/30/2022 JOHN JANSON
CofO Corrected 11/30/2022 JOHN JANSON
Permit Finaled 11/30/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/3/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/3/2019 GUILLERMO PETRA
Sewer availability Cleared 7/3/2019 GUILLERMO PETRA

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/12/2021 Approved STEVEN BACK
Footing/Foundation/Slab 11/23/2021 Approved JEFFREY PARD
ELECTRICAL-Rough 2/23/2022 Approved DAVID SCANTLIN
PLUMBING-Rough 2/23/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/15/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Approved STEVEN BACK
HVAC-Rough 3/15/2022 Approved STEVEN BACK
Interior/Exterior Lathing 3/15/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/24/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 7/1/2022 Approved STEVEN BACK
Green Building Rough 7/1/2022 Approved STEVEN BACK
Insulation 7/1/2022 Approved STEVEN BACK
Drywall Nailing 7/8/2022 Approved MICHAEL SMITH
ELECTRICAL-Final 10/18/2022 Corrections Issued STEVEN BACK
Final 10/18/2022 Not Ready for Inspection STEVEN BACK
Green Building Final 10/18/2022 Approved STEVEN BACK
HVAC-Final 10/18/2022 Approved STEVEN BACK
PLUMBING-Final 10/18/2022 Corrections Issued STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 10/18/2022 Approved STEVEN BACK
ELECTRICAL-Final 11/15/2022 Corrections Issued HENRY KIM
Final 11/15/2022 Corrections Issued HENRY KIM
HVAC-Final 11/15/2022 Approved HENRY KIM
PLUMBING-Final 11/15/2022 Approved HENRY KIM
ELECTRICAL-Final 11/22/2022 Approved STEVEN BACK
Final 11/22/2022 OK to Issue CofO STEVEN BACK
HVAC-Final 11/22/2022 Approved ALEXANDER HANDY
PLUMBING-Final 11/22/2022 Approved STEVEN BACK