751 N GARDNER ST 90046

Certificate Information: 751 N GARDNER ST 90046

Application / Permit
19014-20000-03410
Plan Check / Job No.
B19VN10592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22' X 14' 3" IRREGULAR-SHAPE ADDITION & INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING TO REMODEL KITCHEN & (1) BATHROOM. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/21/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/31/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/25/2019 GURUNATH NESARAJAH
Corrections Issued 6/25/2019 GURUNATH NESARAJAH
Plan Check Approved 6/25/2019 GURUNATH NESARAJAH
Issued 10/21/2019 LADBS
CofO in Progress 3/17/2021 CHRIS CHRISTENSEN
Permit Finaled 3/31/2021 DEROLD HAUFF
Permit Finaled 3/31/2021 DEROLD HAUFF
CofO Issued 3/31/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/25/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 6/25/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 6/25/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor M Vision Construction; Lic. No.: 1004743-B 5470 ALVERN CIR      LOS ANGELES, CA 90045
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2019 Corrections Issued JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 12/11/2019 Approved JOSEPH MCGARRY
PLUMBING-Rough 1/27/2020 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 1/29/2020 Partial Approval RAUL BARAJAS
Insulation 2/5/2020 Partial Approval ARTHUR SARGSYAN
Wood Frame 2/5/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2020 Conditional Approval ARTHUR SARGSYAN
Green Building Rough 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 3/3/2020 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 8/18/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/18/2020 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 8/18/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 8/18/2020 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 8/18/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 8/18/2020 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Partial Approval CHRIS CHRISTENSEN
Rough-Elec/Plmb/HVAC 9/9/2020 Approved CHRIS CHRISTENSEN
Wood Frame 9/9/2020 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/22/2020 Approved CHRIS CHRISTENSEN
Shower Pan 9/22/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/23/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/9/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 11/9/2020 Approved CHRIS CHRISTENSEN
Insulation 11/9/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/9/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/12/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 11/12/2020 Approved CHRIS CHRISTENSEN
Final 2/16/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/16/2021 Approved CHRIS CHRISTENSEN
Green Building Final 2/16/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 2/16/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 2/16/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/16/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 2/16/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 3/16/2021 Approved CHRIS CHRISTENSEN
Final 3/16/2021 OK to Issue CofO CHRIS CHRISTENSEN
HVAC-Final 3/16/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 3/16/2021 Approved CHRIS CHRISTENSEN