8527 W MELVIL ST 90034

Certificate Information: 8527 W MELVIL ST 90034

Application / Permit
19014-20000-03390
Plan Check / Job No.
B19VN10536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15'-9" x 18' TO DETACHED 10' x 18' 1-CAR GARAGE, REFRAME ROOF AND CONVERT TO EXTERIOR ACCESS STORAGE ROOM, LAUNDRY ROOM AND ACCESSORY DWELLING UNIT PER AB494 & SB229. ALL WORKS ARE PER DESIGN. SEE COMMENTS
Permit Issued
Issued on 10/24/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/25/2019 ALDOUS CHIC
Corrections Issued 6/25/2019 ALDOUS CHIC
Applicant returned to address corrections 9/19/2019 ANGELICA DAVE
Plan Check Approved 10/8/2019 HAYATO TSUCHIYA
Issued 10/24/2019 LADBS
CofO in Progress 11/4/2021 EVAN COOPER
No Progress 11/9/2021 KENNETH NAGLE
CofO in Progress 11/30/2021 KENNETH NAGLE
Permit Finaled 11/30/2021 KENNETH NAGLE
CofO Issued 11/30/2021 KENNETH NAGLE
Permit Finaled 11/30/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 6/26/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 10/8/2019 SAFA JAVANMARDI

Contact Information

Architect Tohill,, Kevin Patrick; Lic. No.: C32787 3790 LIGHTNING RIDGE WAY      SIMI VALLEY, CA 93063
Contractor Precision Design & Build Inc; Lic. No.: 1036946-B 5455 WILSHIRE BLVD   #2132    LOS ANGELES, CA 90036
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/27/2019 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 12/30/2019 Corrections Issued EVAN COOPER
Pre-Inspection 1/27/2020 Corrections Issued MICHAEL TEMPLE
Pre-Inspection 3/24/2020 Partial Inspection EVAN COOPER
PLUMBING-Rough 12/4/2020 Partial Approval EVAN COOPER
Rough-Elec/Plmb/HVAC 12/4/2020 Approved EVAN COOPER
Footing/Foundation/Slab 12/10/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 1/11/2021 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/11/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 1/11/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 1/11/2021 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 2/25/2021 Corrections Issued EVAN COOPER
HVAC-Rough 2/25/2021 Approved EVAN COOPER
PLUMBING-Rough 2/25/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 3/3/2021 Approved EVAN COOPER
Green Building Rough 3/3/2021 Approved EVAN COOPER
Interior/Exterior Lathing 3/3/2021 Partial Approval EVAN COOPER
Shower Pan 3/3/2021 Not Ready for Inspection EVAN COOPER
Insulation 3/8/2021 Approved EVAN COOPER
Shower Pan 3/8/2021 Approved EVAN COOPER
Drywall Nailing 3/11/2021 Approved EVAN COOPER
Interior/Exterior Lathing 3/11/2021 Approved EVAN COOPER
Underground Mechanical 5/21/2021 Partial Approval EVAN COOPER
Underground Mechanical 6/4/2021 Partial Approval EVAN COOPER
Sewer 7/20/2021 Corrections Issued PIERRE VEGA
Sewer 7/22/2021 Approved JOHN KIDWELL
Service/Power Release 8/27/2021 Approved EVAN COOPER
Final 9/23/2021 Corrections Issued EVAN COOPER
Green Building Final 9/23/2021 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready EVAN COOPER
Smoke Detectors 9/23/2021 Approved EVAN COOPER
ELECTRICAL-Final 10/7/2021 Approved EVAN COOPER
Final 10/7/2021 Conditional Approval EVAN COOPER
Green Building Final 10/7/2021 Approved EVAN COOPER
HVAC-Final 10/7/2021 Approved EVAN COOPER
PLUMBING-Final 10/7/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/7/2021 SGSOV Approved EVAN COOPER