5801 N KEOKUK AVE 91367

Certificate Information: 5801 N KEOKUK AVE 91367

Application / Permit
19014-20000-03382
Plan Check / Job No.
B19VN10508
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition/Altaration to (E) Single Family Dwelling. New (13'6" x 18'6" irregular) ground floor addition including (4' x 7'6") covered Porch. New (33'6" x 33'9" irregular) second-story addition.
Permit Issued
Issued on 8/29/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 7/15/2019 LUIS RINCON
Corrections Issued 7/16/2019 LUIS RINCON
Quality Review Completed 7/18/2019 OMID HEDAYAT
Building Plans Picked Up 7/31/2019 APPLICANT
Green Plans Picked Up 7/31/2019 APPLICANT
Plan Check Approved 8/28/2019 LUIS RINCON
Issued 8/29/2019 LADBS
CofO in Progress 7/9/2020 HENRY KIM
Permit Finaled 7/10/2020 JOHN JANSON
CofO Issued 7/10/2020 JOHN JANSON
Permit Finaled 7/10/2020 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 8/15/2019 PARISA ZAHABI
Eng Process Fee Ord 176,300 Cleared 8/16/2019 LEE GUILBEAUX
Sewer availability Cleared 8/16/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 8/27/2019 BARTON HOLMES
Low Impact Development Cleared 8/27/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 8/28/2019 JULIUS GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Vasquez,, Luis Fernando; Lic. No.: C56232 1551 RANDALL ST      GLENDALE, CA 91201
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2019 Corrections Issued JOHN JANSON
Footing/Foundation/Slab 10/7/2019 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/16/2019 Partial Approval SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 10/21/2019 Partial Approval JOHN JANSON
Floor/Roof Diaphrgm/Shear Wall 11/4/2019 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/23/2019 Corrections Issued HENRY KIM
ELECTRICAL-Rough 12/23/2019 Approved HENRY KIM
Green Building Rough 12/23/2019 Not Ready for Inspection HENRY KIM
HVAC-Rough 12/23/2019 Conditional Approval HENRY KIM
BUILDING-Rough-Frame 1/15/2020 Approved HENRY KIM
Green Building Rough 1/15/2020 Approved HENRY KIM
PLUMBING-Rough 1/15/2020 Approved HENRY KIM
Sewer 1/15/2020 Approved HENRY KIM
Insulation 2/6/2020 Partial Approval HENRY KIM
Interior/Exterior Lathing 2/6/2020 Approved HENRY KIM
Shower Pan 2/6/2020 Not Ready for Inspection HENRY KIM
Drywall Nailing 2/14/2020 Approved HENRY KIM
Insulation 2/14/2020 Approved HENRY KIM
Interior/Exterior Lathing 2/14/2020 Approved HENRY KIM
Shower Pan 2/14/2020 Approved HENRY KIM
ELECTRICAL-Final 5/8/2020 Not Ready for Inspection HENRY KIM
HVAC-Final 5/8/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Final 5/8/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 6/9/2020 Not Ready for Inspection HENRY KIM
HVAC-Final 6/9/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Final 6/9/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 6/19/2020 Corrections Issued HENRY KIM
Final 6/19/2020 Corrections Issued HENRY KIM
Green Building Final 6/19/2020 Approved HENRY KIM
HVAC-Final 6/19/2020 Corrections Issued HENRY KIM
PLUMBING-Final 6/19/2020 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Approved HENRY KIM
Smoke Detectors 6/19/2020 Corrections Issued HENRY KIM
ELECTRICAL-Final 6/24/2020 Approved HENRY KIM
Final 6/24/2020 Not Ready for Inspection HENRY KIM
HVAC-Final 6/24/2020 Approved HENRY KIM
PLUMBING-Final 6/24/2020 Approved HENRY KIM
Smoke Detectors 6/24/2020 Approved HENRY KIM
Final 6/29/2020 Corrections Issued HENRY KIM
Final 7/9/2020 OK to Issue CofO HENRY KIM