7835 W OWENS ST 91040

Certificate Information: 7835 W OWENS ST 91040

Application / Permit
19014-20000-03374
Plan Check / Job No.
B19VN10468
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16' X 21'6" ADD TO & CONVERT 20' X 20' GARAGE TO (N) 36' X 24'6" IRR. SHAPE ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 8/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 6/24/2019 PINANK PATEL
Corrections Issued 6/24/2019 PINANK PATEL
Building Plans Picked Up 6/26/2019 APPLICANT
Plan Check Approved 8/6/2019 PINANK PATEL
Issued 8/7/2019 LADBS
CofO in Progress 9/3/2020 MATTHEW NELSON
Permit Finaled 11/21/2020 MICHAEL SMITH
CofO Issued 11/21/2020 MICHAEL SMITH
Permit Finaled 11/21/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/8/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/8/2019 LEE GUILBEAUX
Sewer availability Cleared 7/8/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/6/2019 GUILLERMO PETRA
Grading Pre-Inspection Cleared 8/6/2019 PINANK PATEL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/13/2020 Partial Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 1/22/2020 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 1/22/2020 Not Ready for Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 1/29/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/18/2020 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 2/18/2020 Approved MATTHEW NELSON
Green Building Rough 2/18/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 3/11/2020 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 3/11/2020 Approved MATTHEW NELSON
PLUMBING-Rough 3/11/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 3/23/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 3/23/2020 Approved MATTHEW NELSON
Gas Test 3/23/2020 Partial Inspection MATTHEW NELSON
HVAC-Rough 3/23/2020 Approved MATTHEW NELSON
PLUMBING-Rough 3/23/2020 Approved MATTHEW NELSON
Insulation 4/2/2020 Approved MATTHEW NELSON
Drywall Nailing 4/6/2020 Approved MATTHEW NELSON
Shower Pan 4/6/2020 Approved MATTHEW NELSON
Final 6/24/2020 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 6/24/2020 Approved MATTHEW NELSON
Green Building Final 6/24/2020 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 6/24/2020 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Not Ready MATTHEW NELSON
ELECTRICAL-Final 8/11/2020 Approved MATTHEW NELSON
Final 8/11/2020 Partial Inspection MATTHEW NELSON
Green Building Final 8/11/2020 Approved MATTHEW NELSON
HVAC-Final 8/11/2020 Approved MATTHEW NELSON
PLUMBING-Final 8/11/2020 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Approved MATTHEW NELSON
Service/Power Release 8/14/2020 Corrections Issued MATTHEW NELSON
Final 9/2/2020 OK to Issue CofO MATTHEW NELSON