4847 N CALHOUN AVE 91423

Certificate Information: 4847 N CALHOUN AVE 91423

Application / Permit
19014-20000-03370
Plan Check / Job No.
B19VN10464
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD IRR. SHAPE 27'-9" x 33'-1" MASTER BED AND BATHROOM AND EXPAND KITCHEN. WORK PER ENGINEER.
Permit Issued
Issued on 7/17/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2019 APPLICANT
Assigned to Plan Check Engineer 6/24/2019 TROY DEGUZMAN
Corrections Issued 6/24/2019 TROY DEGUZMAN
Plan Check Approved 7/15/2019 ANGELICA MARTINEZ
Issued 7/17/2019 LADBS
CofO in Progress 2/17/2021 JENNIFER RABUCHIN
CofO Issued 3/27/2021 MICHAEL SMITH
Permit Finaled 3/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2019 CELINA MORENO
Hydrant and Access approval Cleared 7/11/2019 GILBERT URREA
Sewer availability Cleared 7/11/2019 CELINA MORENO
ZI Cleared 7/12/2019 ANNA VIDAL
Low Impact Development Cleared 7/15/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 7/15/2019 ERIK BEASLEY

Contact Information

Engineer Andrejic,, Milos M; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2019 Not Ready for Inspection THOMAS FINNILA
Footing/Foundation/Slab 7/24/2019 Approved THOMAS FINNILA
BUILDING-Rough-Frame 7/31/2019 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/31/2019 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 7/31/2019 Not Ready for Inspection THOMAS FINNILA
Wood Frame 7/31/2019 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/2/2019 Partial Approval THOMAS FINNILA
PLUMBING-Rough 8/12/2019 Partial Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/21/2019 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 10/29/2019 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 10/29/2019 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 11/12/2019 No Access for Inspection MATTHEW NUCKOLLS
Green Building Rough 11/12/2019 No Access for Inspection MATTHEW NUCKOLLS
Pre-Inspection 11/14/2019 Partial Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 12/9/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 12/9/2019 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2019 Partial Approval CHARLES POWELL
PLUMBING-Rough 12/11/2019 Corrections Issued CHARLES POWELL
Interior/Exterior Lathing 1/17/2020 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 1/17/2020 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/21/2020 Partial Approval CHARLES POWELL
Deck 5/21/2020 Corrections Issued CHARLES POWELL
Green Building Rough 5/21/2020 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 5/29/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 6/8/2020 Partial Inspection CHARLES POWELL
ELECTRICAL-Rough 6/8/2020 Partial Approval CHARLES POWELL
HVAC-Rough 6/8/2020 Approved CHARLES POWELL
PLUMBING-Rough 6/8/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 6/15/2020 Approved CHARLES POWELL
Green Building Rough 6/15/2020 Not Ready for Inspection CHARLES POWELL
Insulation 6/18/2020 Approved CHARLES POWELL
Drywall Nailing 6/26/2020 Partial Approval CHARLES POWELL
Green Building Rough 6/26/2020 Not Ready for Inspection CHARLES POWELL
Interior/Exterior Lathing 7/14/2020 Not Ready for Inspection JOHN HAYES
Deck 9/11/2020 Corrections Issued CHARLES POWELL
Deck 9/16/2020 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
Drywall Nailing 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
Final 11/6/2020 Corrections Issued BRENDAN LOONEY
Green Building Final 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 11/6/2020 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 11/6/2020 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 11/24/2020 Approved THOMAS FINNILA
Drywall Nailing 11/24/2020 Approved THOMAS FINNILA
Green Building Rough 11/24/2020 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 11/24/2020 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/1/2020 SGSOV Not Ready CHARLES POWELL
Final 1/13/2021 Corrections Issued BEAU COLLINS
Green Building Final 1/13/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 1/13/2021 SGSOV Approved BEAU COLLINS
Smoke Detectors 1/13/2021 Approved BEAU COLLINS
ELECTRICAL-Final 2/16/2021 Approved JENNIFER RABUCHIN
Final 2/16/2021 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 2/16/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/16/2021 Approved JENNIFER RABUCHIN