4546 N WORTSER AVE 91604
Certificate Information: 4546 N WORTSER AVE 91604
- Application / Permit
- 19014-20000-03281
- Plan Check / Job No.
- B19VN10198
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE/STORAGE AND CONVERT IRREGULAR 16'8"x32'1" TO ACCESSORY DWELLING UNIT, ADD (N) IRREGULAR 20'7" x 16'8" 2ND-STORY RECREATIONAL ROOM. 9'3" x 18' GARAGE TO REMAIN.
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | LUIS RINCON |
| Corrections Issued | 8/9/2019 | LUIS RINCON |
| Quality Review Completed | 8/12/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 8/21/2019 | APPLICANT |
| Green Plans Picked Up | 8/21/2019 | APPLICANT |
| Plan Check Approved | 1/3/2020 | LUIS RINCON |
| Issued | 2/14/2020 | LADBS |
| CofO in Progress | 8/26/2021 | ARAM AVEDISIAN |
| Permit Finaled | 1/8/2022 | MICHAEL SMITH |
| CofO Issued | 1/8/2022 | MICHAEL SMITH |
| Permit Finaled | 1/8/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/6/2019 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/25/2019 | SARAH YOUSSEF |
| Address approval | Cleared | 12/6/2019 | GUILLERMO PETRA |
| ZI | Cleared | 12/6/2019 | HERMINIGILDO AGUSTIN |
| Green Code | Cleared | 12/11/2019 | DAVID MATSON |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/13/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 12/17/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/3/2020 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Approved | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Partial Approval | RAYMOND KEHOE |
| PLUMBING-Rough | 4/23/2020 | Corrections Issued | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2020 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 4/30/2020 | Corrections Issued | JEFFREY PARD |
| BUILDING-Rough-Frame | 5/14/2020 | Corrections Issued | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 5/14/2020 | Corrections Issued | ROBERT MINASSIANS |
| Green Building Rough | 5/14/2020 | Not Ready for Inspection | ROBERT MINASSIANS |
| HVAC-Rough | 5/14/2020 | Corrections Issued | ROBERT MINASSIANS |
| PLUMBING-Rough | 5/14/2020 | Corrections Issued | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 5/20/2020 | Approved | RAYMOND KEHOE |
| HVAC-Rough | 5/20/2020 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 5/20/2020 | Approved | RAYMOND KEHOE |
| Wood Frame | 5/20/2020 | Approved | RAYMOND KEHOE |
| Insulation | 5/27/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/27/2020 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 6/11/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/11/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/11/2020 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 6/11/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/21/2020 | Approved | BEAU COLLINS |
| Sewer | 7/21/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 5/24/2021 | Approved | ARAM AVEDISIAN |
| Final | 5/24/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/24/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 5/24/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 5/24/2021 | Approved | ARAM AVEDISIAN |
| Final | 7/22/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Final | 7/22/2021 | Approved | ARAM AVEDISIAN |
| Final | 8/26/2021 | OK to Issue CofO | ARAM AVEDISIAN |