627 W 76TH ST UNITS #1-4 90044

Certificate Information: 627 W 76TH ST UNITS #1-4 90044

Application / Permit
19014-20000-03279
Plan Check / Job No.
B19VN10192
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 37'9" X 19' THIRD FLOOR ADDITION OF ONE UNIT TO (E) DUPLEX TO CONVERT TO (3) UNIT APARTMENT, ADD 10' X 10' BREEZWAY TO CONNECT TO (3) UNIT APARTMENT TO THE SFD TO CREATE A (4) UNIT APARTMENT , NEW 9' X 20' ADDITION OF A (2) CAR GARAGE TO (E) (2 CAR GARAGE TO CREATE A (4) CAR GARAGE, NEW 23' X 9' ENCLOSED STAIRCASE , NFPA-13 FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 10/22/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/18/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 RARES BODEA
Corrections Issued 7/14/2019 RARES BODEA
Quality Review Completed 7/15/2019 OMID HEDAYAT
Building Plans Picked Up 7/22/2019 APPLICANT
Applicant returned to address corrections 8/2/2019 RARES BODEA
Applicant returned to address corrections 9/10/2019 RARES BODEA
Applicant returned to address corrections 9/19/2019 RARES BODEA
Applicant returned to address corrections 10/10/2019 RARES BODEA
Applicant returned to address corrections 10/21/2019 RARES BODEA
Plan Check Approved 10/21/2019 RARES BODEA
Issued 10/22/2019 LADBS
CofO in Progress 8/12/2025 ERNESTO CORRAL
CofO Issued 8/12/2025 ERNESTO CORRAL
Permit Finaled 8/12/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/23/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/23/2019 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 7/23/2019 RICHARD REASER
Housing rent stabilization Cleared 7/23/2019 ISMAEL HERNANDEZ
Hydrant and Access approval Cleared 7/23/2019 JOHN CONNEALLY
Sewer availability Cleared 7/23/2019 ADRIAN SANCHEZ
"Q" conditions Cleared 8/2/2019 RINA LARA
Low Impact Development Cleared 8/12/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 8/12/2019 KAREN LE
Green Code Cleared 8/20/2019 DAVID MATSON
Address approval Cleared 9/19/2019 GABRIEL ROBLES
Low Impact Development Cleared 9/24/2019 JORGE MEJIA LEMUS
Highway dedication Cleared 10/7/2019 CELINA MORENO
Fire Marshall Fire Life Safety Cleared 10/16/2019 PEJMAN NOORI

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/28/2019 Partial Approval JOEY BUCHANAN
Insulation 10/30/2019 Partial Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 12/5/2019 Not Ready for Inspection JOEY BUCHANAN
Pre-Inspection 12/5/2019 Corrections Issued RUSSELL BONVOULOIR
Green Building Rough 12/9/2019 Partial Approval RUSSELL BONVOULOIR
Wood Frame 12/9/2019 Partial Approval RUSSELL BONVOULOIR
Interior/Exterior Lathing 12/13/2019 Approved RUSSELL BONVOULOIR
Green Building Rough 7/6/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Wood Frame 7/6/2020 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Rough 8/26/2020 Approved LEOPOLDO MENDOZA
Wood Frame 8/26/2020 Conditional Approval LEOPOLDO MENDOZA
Insulation 10/1/2020 Approved LEOPOLDO MENDOZA
Drywall Nailing 10/6/2020 Approved LEOPOLDO MENDOZA
Interior/Exterior Lathing 10/15/2020 Approved LEOPOLDO MENDOZA
Footing/Foundation/Slab 12/10/2020 Approved LANNY MERRICK
Final 5/19/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 5/19/2021 Approved LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Not Ready LEOPOLDO MENDOZA
Smoke Detectors 5/19/2021 Approved LEOPOLDO MENDOZA
Wood Frame 5/19/2021 Approved LEOPOLDO MENDOZA
Final 4/14/2022 Partial Inspection RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 4/14/2022 SGSOV Not Ready RUSSELL BONVOULOIR
Final 1/11/2023 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 1/11/2023 SGSOV Approved ALAN MORELOS
Special/Order Compliance 2/7/2024 Not Ready for Inspection LUIS CCAMACHO
Final 6/21/2024 Corrections Issued DARRYL ARNOLD
Final 8/12/2025 OK to Issue CofO ERNESTO CORRAL