1011 N ROSCOMARE ROAD 90077
Certificate Information: 1011 N ROSCOMARE ROAD 90077
- Application / Permit
- 19014-20000-03214
- Plan Check / Job No.
- B19VN09962
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Recongifure ground floor with addition of total 103.5 SF (RFA) at numerous locations; add irregular shape 65'9" x 42.5' new 2nd floor for laundry room, bedrooms and bathrooms.
- Permit Issued
- Issued on 1/15/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Green Plans Picked Up | 6/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | ALDOUS CHIC |
| Corrections Issued | 7/8/2019 | ALDOUS CHIC |
| Quality Review Completed | 7/10/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 7/10/2019 | APPLICANT |
| Applicant returned to address corrections | 10/3/2019 | ALDOUS CHIC |
| Plan Check Approved | 10/31/2019 | ALDOUS CHIC |
| Issued | 1/15/2020 | LADBS |
| CofO in Progress | 2/22/2022 | CARLOS MATAMOROS |
| CofO in Progress | 2/22/2022 | CARLOS MATAMOROS |
| Permit Finaled | 2/28/2022 | DANIEL ORRANTE |
| CofO Issued | 2/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/30/2019 | JULIUS GARCIA |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | JULIUS GARCIA |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | JULIUS GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/30/2019 | JULIUS GARCIA |
| Highway dedication | Cleared | 8/30/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 8/30/2019 | JULIUS GARCIA |
| Hydrant and Access approval | Cleared | 9/12/2019 | GILBERT URREA |
| Low Impact Development | Cleared | 9/18/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/20/2019 | SAFA JAVANMARDI |
| Green Code | Cleared | 9/24/2019 | PARISA ZAHABI |
| Grading Pre-Inspection | Cleared | 9/25/2019 | ALDOUS CHIC |
| GPI Written Notices | Cleared | 10/3/2019 | ALDOUS CHIC |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cai,, Luo B; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Charifa,, Rizaldy Dizon; Lic. No.: C62585 | 815 W CESAR E CHAVEZ AVE STE 205 LOS ANGELES, CA 90012 |
| Engineer | Montemayor,, G F; Lic. No.: C25258 | 1617 S WAVERLY GLEN WAY HACIENDA HEIGHTS, CA 91745 |
| Engineer | Yuzon,, Benigno S; Lic. No.: C38991 | 25531 PRADO DELASBELLOTAS CALABASAS, CA 91302 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 3/6/2020 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 3/17/2020 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 5/6/2020 | Corrections Issued | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 5/7/2020 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/3/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Inspection | 8/3/2020 | Approved | CARLOS MATAMOROS |
| Piling/Pier/Caisson | 8/6/2020 | Partial Approval | CARLOS MATAMOROS |
| Deputy Reinf. Concrete | 8/7/2020 | Conditional Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/17/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/17/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/18/2020 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/29/2020 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 9/29/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 9/29/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/29/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2020 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2020 | Corrections Issued | CARLOS MATAMOROS |
| Wood Frame | 11/18/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/24/2020 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 12/2/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 12/2/2020 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 12/2/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 12/4/2020 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/4/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 12/4/2020 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 12/5/2020 | Partial Inspection | CHRISTOPHER WILSON |
| HVAC-Rough | 12/9/2020 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/9/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 12/10/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 12/10/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/11/2020 | Conditional Approval | CARLOS MATAMOROS |
| Green Building Rough | 12/11/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Insulation | 12/15/2020 | Partial Approval | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 12/15/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 12/15/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 12/16/2020 | Approved | CARLOS MATAMOROS |
| Insulation | 12/18/2020 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 12/21/2020 | Corrections Issued | CARLOS MATAMOROS |
| Drywall Nailing | 12/24/2020 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 2/10/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/10/2021 | Corrections Issued | CARLOS MATAMOROS |
| Sewer | 2/10/2021 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 2/12/2021 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 2/13/2021 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 2/13/2021 | Partial Inspection | HENRY KIM |
| Pre-Inspection | 2/16/2021 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 3/23/2021 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 3/30/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/16/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/4/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 5/4/2021 | Partial Approval | CARLOS MATAMOROS |
| Service/Power Release | 6/1/2021 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 12/6/2021 | Approved | CARLOS MATAMOROS |
| Final | 12/6/2021 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 12/6/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 12/6/2021 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 12/6/2021 | Partial Approval | CARLOS MATAMOROS |
| Final | 12/8/2021 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Inspection | 12/8/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Final | 2/11/2022 | Approved | CARLOS MATAMOROS |
| Final | 2/11/2022 | OK to Issue CofO | CARLOS MATAMOROS |
| Green Building Final | 2/11/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 2/11/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 2/11/2022 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 2/11/2022 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 2/15/2022 | Corrections Issued | CARLOS MATAMOROS |