6918 N TEESDALE AVE 91605
Certificate Information: 6918 N TEESDALE AVE 91605
- Application / Permit
- 19014-20000-03200
- Plan Check / Job No.
- B19VN09922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 12' X 30'-9" ADDITION TO (E) SFD TO ENLARGE LIVING & DINING ROOM, NEW BATHROOM & LAUNDRY ROOM. EXPAND KITCHEN PER PLAN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/14/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2019 | RAPHAEL ROSAS |
| Issued | 6/14/2019 | LADBS |
| CofO in Progress | 5/17/2021 | JENNIFER RABUCHIN |
| CofO Issued | 6/19/2021 | MICHAEL SMITH |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 6/14/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2019 | Approved | GREG ALLTON |
| BUILDING-Rough-Frame | 7/26/2019 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 7/26/2019 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/27/2019 | Partial Inspection | GREG ALLTON |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2019 | Partial Approval | GREG ALLTON |
| Green Building Rough | 8/27/2019 | Not Ready for Inspection | GREG ALLTON |
| Interior/Exterior Lathing | 9/25/2019 | Not Ready for Inspection | GREG ALLTON |
| Interior/Exterior Lathing | 9/26/2019 | Conditional Approval | GREG ALLTON |
| HVAC-Rough | 11/25/2019 | Partial Approval | GREG ALLTON |
| ELECTRICAL-Rough | 12/3/2019 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 12/3/2019 | Approved | RAYMOND KEHOE |
| Insulation | 1/15/2020 | Partial Approval | GREG ALLTON |
| Drywall Nailing | 2/5/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 2/5/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 4/16/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 4/16/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/16/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/16/2021 | Corrections Issued | RICHARD DOCKUS |
| ELECTRICAL-Final | 5/14/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/14/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/14/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/14/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/14/2021 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 5/14/2021 | Approved | JENNIFER RABUCHIN |