7328 N WHITE OAK AVE 91406
Certificate Information: 7328 N WHITE OAK AVE 91406
- Application / Permit
- 19014-20000-03178
- Plan Check / Job No.
- B19VN09847
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/2/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/11/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 6/13/2019 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 6/24/2019 | APPLICANT |
| Plan Check Approved | 1/2/2020 | SAMUEL GONZALEZ |
| Issued | 1/2/2020 | LADBS |
| CofO in Progress | 7/29/2020 | JACK KARGODORIAN |
| CofO Issued | 8/11/2020 | MICHAEL SMITH |
| Permit Finaled | 8/11/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 11/7/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/18/2020 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/24/2020 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 3/20/2020 | Corrections Issued | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | ROBERT MINASSIANS |
| Green Building Rough | 3/20/2020 | Partial Approval | ROBERT MINASSIANS |
| Gas Test | 3/26/2020 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/26/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/27/2020 | Corrections Issued | MARK JOHNSON |
| ELECTRICAL-Rough | 3/27/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 3/27/2020 | Approved | MARK JOHNSON |
| HVAC-Rough | 4/2/2020 | Approved | MARK JOHNSON |
| Insulation | 4/6/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/16/2020 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/16/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/8/2020 | Partial Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/8/2020 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/8/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/8/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 5/8/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/8/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/8/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/8/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/22/2020 | Approved | THOMAS FINNILA |
| Final | 5/22/2020 | Partial Inspection | THOMAS FINNILA |
| Green Building Final | 5/22/2020 | Approved | THOMAS FINNILA |
| Final | 7/29/2020 | OK to Issue CofO | JACK KARGODORIAN |