14925 W SYLVAN ST 91411
Certificate Information: 14925 W SYLVAN ST 91411
- Application / Permit
- 19014-20000-03158
- Plan Check / Job No.
- B19VN09762
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 12' x 20' ADDITION & CONVERT DET. GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/11/2019
- Issuing Office
- Valley
- Current Status
- Issued on 7/11/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2019 | JEFFREY TANGONAN |
| Corrections Issued | 6/12/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 6/17/2019 | APPLICANT |
| Issued | 7/11/2019 | LADBS |
Permit Application Clearance Information
| Address approval | Cleared | 7/10/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2019 | APEKSHYA BAJRACHARYA |
| Roof/Waste drainage to street | Cleared | 7/10/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 7/10/2019 | APEKSHYA BAJRACHARYA |
Contact Information
| Contractor | Ochoa Victor Manuel; Lic. No.: 908306-B | 13700 FOOTHILL BLVD #920151 SYLMAR, CA 91342 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2020 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/19/2020 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/27/2020 | No Access for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/4/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/12/2020 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/22/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/3/2020 | Partial Inspection | PIERRE VEGA |
| Footing/Foundation/Slab | 1/27/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 2/12/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| PLUMBING-Rough | 2/19/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/15/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Pre-Inspection | 3/22/2021 | Partial Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/12/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 4/20/2021 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 4/20/2021 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/12/2021 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/12/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/12/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/7/2021 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 6/7/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 1/24/2022 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 1/24/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 1/24/2022 | Approved | RICHARD DOCKUS |
| Rough-Elec/Plmb/HVAC | 1/24/2022 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/16/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 5/16/2022 | Approved | RICHARD DOCKUS |
| Final | 5/16/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 5/16/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 5/16/2022 | Approved | RICHARD DOCKUS |
| Final | 6/29/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Final | 7/6/2022 | Partial Approval | DEANDRE HOFFMAN |
| Final | 7/6/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Final | 7/6/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/22/2022 | Approved | RICHARD DOCKUS |
| Final | 8/22/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| PLUMBING-Final | 8/22/2022 | Approved | RICHARD DOCKUS |