10022-10024 N PALI AVE 91042

Certificate Information: 10022-10024 N PALI AVE 91042

Application / Permit
19014-20000-03148
Plan Check / Job No.
B19VN09719
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 1'-6" X 20' ON FIRST FLOOR OF GARAGE AND 20' X 21' ON SECOND FLOOR AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 8/21/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 SELLA BENYAMIN
Corrections Issued 7/9/2019 SELLA BENYAMIN
Quality Review Completed 7/9/2019 STEVEN KIM
Building Plans Picked Up 7/10/2019 APPLICANT
Plan Check Approved 8/8/2019 SELLA BENYAMIN
Issued 8/21/2019 LADBS
CofO in Progress 3/5/2021 MATTHEW NELSON
CofO in Progress 3/11/2021 MATTHEW NELSON
CofO in Progress 3/11/2021 MATTHEW NELSON
No Progress 3/11/2021 MATTHEW NELSON
CofO in Progress 3/11/2021 MATTHEW NELSON
Permit Finaled 5/8/2021 MICHAEL SMITH
CofO Issued 5/8/2021 MICHAEL SMITH
Permit Finaled 5/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/16/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/16/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/16/2019 LEE GUILBEAUX
Sewer availability Cleared 7/16/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/16/2019 LEE GUILBEAUX
Green Code Cleared 7/30/2019 DAVID MATSON
Grading Pre-Inspection Cleared 8/8/2019 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/27/2020 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 2/25/2020 Corrections Issued MATTHEW NELSON
Special/Order Compliance 2/25/2020 Approved PIERRE VEGA
Footing/Foundation/Slab 3/6/2020 Approved MATTHEW NELSON
PLUMBING-Rough 3/6/2020 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 3/11/2020 Approved MATTHEW NELSON
PLUMBING-Rough 3/11/2020 Partial Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Not Ready for Inspection MATTHEW NELSON
Special/Order Compliance 5/11/2020 Approved GREGG CUMMINGS
Wood Frame 5/11/2020 Partial Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Approved MATTHEW NELSON
PLUMBING-Rough 6/19/2020 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 6/22/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 7/8/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 7/14/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/16/2020 Approved MATTHEW NELSON
HVAC-Rough 7/21/2020 Approved MATTHEW NELSON
Insulation 7/27/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/30/2020 Approved BEAU COLLINS
Drywall Nailing 8/14/2020 Approved MATTHEW NELSON
Shower Pan 8/25/2020 Approved MATTHEW NELSON
Shower Pan 9/9/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 2/22/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 3/4/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 3/4/2021 Approved MATTHEW NELSON
Final 3/4/2021 OK to Issue CofO MATTHEW NELSON
Green Building Final 3/4/2021 Approved MATTHEW NELSON
Green Building Rough 3/4/2021 Approved MATTHEW NELSON
HVAC-Final 3/4/2021 Approved MATTHEW NELSON
PLUMBING-Final 3/4/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/4/2021 Approved MATTHEW NELSON