4252 N COLBATH AVE 91423

Certificate Information: 4252 N COLBATH AVE 91423

Application / Permit
19014-20000-03146
Plan Check / Job No.
B19VN09718
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodeling; remove all on grade structures except garage walls and total 11.33' (L) portion of exterior walls, rebuild dwelling with addition of 9'2" x 8'1" on ground irregular shape 47'5' x 38' new 2nd floor.
Permit Issued
Issued on 9/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 1/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 ALDOUS CHIC
Corrections Issued 7/8/2019 ALDOUS CHIC
Quality Review Completed 7/10/2019 ABDUL CHEGENI
Building Plans Picked Up 7/16/2019 APPLICANT
Plan Check Approved 9/5/2019 ALDOUS CHIC
Issued 9/6/2019 LADBS
CofO in Progress 11/5/2021 MICHAEL PELHAM
CofO in Progress 11/9/2021 MISAEL ESPARZA
Permit Finaled 1/10/2022 MICHAEL SMITH
CofO Issued 1/10/2022 MICHAEL SMITH
Permit Finaled 1/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/25/2019 ALDOUS CHIC
Eng Process Fee Ord 176,300 Cleared 7/29/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/29/2019 MARKOS PEREZ-BRAN
Green Code Cleared 8/22/2019 MICHAEL AYERS
Low Impact Development Cleared 8/29/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 8/29/2019 JEANETTE VONG
GPI Written Notices Cleared 9/5/2019 ALDOUS CHIC

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2019 Approved THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 12/20/2019 Partial Approval JEFFREY PARD
Excavation/Setback/Form/Re-Bar 2/11/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 2/11/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 2/14/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 2/19/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 2/19/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 2/21/2020 Partial Approval CHARLES POWELL
Insulation 2/21/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/25/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/7/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 5/27/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Corrections Issued CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/29/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 8/31/2020 Approved CHARLES POWELL
PLUMBING-Rough 8/31/2020 Corrections Issued CHARLES POWELL
HVAC-Rough 9/4/2020 Approved CHARLES POWELL
PLUMBING-Rough 9/4/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/10/2020 Approved CHARLES POWELL
Green Building Rough 9/10/2020 Not Ready for Inspection CHARLES POWELL
Interior/Exterior Lathing 9/10/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 9/28/2020 Approved CHARLES POWELL
Green Building Rough 9/28/2020 Partial Approval CHARLES POWELL
Insulation 10/2/2020 No Access for Inspection ARAM AVEDISIAN
Green Building Rough 10/6/2020 Approved ARAM AVEDISIAN
Insulation 10/6/2020 Approved ARAM AVEDISIAN
Drywall Nailing 10/15/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 11/17/2020 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 12/24/2020 Approved JOHN HAYES
Shower Pan 12/24/2020 Approved JOHN HAYES
Footing/Foundation/Slab 6/17/2021 Partial Approval CHARLES POWELL
Masonry Wall/Backfill 6/23/2021 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 7/15/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 8/20/2021 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 8/20/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 8/23/2021 Approved CHARLES POWELL
HVAC-Final 8/23/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Final 8/26/2021 Approved CHARLES POWELL
PLUMBING-Final 9/14/2021 Approved ARAM AVEDISIAN
Final 10/13/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/13/2021 Approved MISAEL ESPARZA
Green Building Final 10/13/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 10/13/2021 Approved MISAEL ESPARZA
Final 10/19/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 10/19/2021 Approved MISAEL ESPARZA
Final 11/4/2021 OK to Issue CofO MISAEL ESPARZA