228 S HUDSON AVE 90004

Certificate Information: 228 S HUDSON AVE 90004

Application / Permit
19014-20000-03107
Plan Check / Job No.
B19VN09605
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel kitchen/bathroom, convert porte cochere to trellis, enclose breezeway between dwelling & garage for laundry room extension, new fire place in family room; reconfigure 2nd floor with addition of irregular shape 26' x 20.5' on top of attached patio cover for new closet/bedroom/bathroom/den. See comment.
Permit Issued
Issued on 2/26/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 ALDOUS CHIC
Corrections Issued 7/1/2019 ALDOUS CHIC
Quality Review Completed 7/2/2019 ABDUL CHEGENI
Building Plans Picked Up 7/3/2019 APPLICANT
Applicant returned to address corrections 1/9/2020 ALDOUS CHIC
Applicant returned to address corrections 1/29/2020 ALDOUS CHIC
Plan Check Approved 2/26/2020 ALDOUS CHIC
Issued 2/26/2020 LADBS
CofO in Progress 1/4/2021 JOSEPH MCGARRY
Permit Finaled 1/11/2021 DEROLD HAUFF
CofO Issued 1/11/2021 DEROLD HAUFF
Permit Finaled 1/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/8/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 7/8/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 7/8/2019 MARKOS PEREZ-BRAN
Green Code Cleared 9/27/2019 DAVID MATSON
CPC Cleared 1/6/2020 SUKI GERSHENHORN
HPOZ Cleared 1/6/2020 SUKI GERSHENHORN
ZI Cleared 1/6/2020 SUKI GERSHENHORN

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 4/20/2020 Approved ARTHUR SARGSYAN
METHANE-Barrier 4/20/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 4/20/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 5/8/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 5/8/2020 Approved ARTHUR SARGSYAN
Green Building Rough 5/8/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 5/8/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 5/8/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/15/2020 Approved THOMAS LOGRASSO
Shower Pan 5/15/2020 Approved THOMAS LOGRASSO
Deputy Drilled-In Anchors 5/28/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2020 Approved ARTHUR SARGSYAN
Deputy Wood Construction 6/5/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 6/9/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 6/9/2020 Approved ARTHUR SARGSYAN
Shower Pan 6/11/2020 Approved THOMAS LOGRASSO
Insulation 6/17/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 6/17/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 6/23/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/17/2020 Approved THOMAS LOGRASSO
ELECTRICAL-Final 12/29/2020 Corrections Issued JOSEPH MCGARRY
Final 12/29/2020 Corrections Issued JOSEPH MCGARRY
Green Building Final 12/29/2020 Approved JOSEPH MCGARRY
HVAC-Final 12/29/2020 Approved JOSEPH MCGARRY
PLUMBING-Final 12/29/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/29/2020 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 12/29/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 12/31/2020 OK to Issue CofO JOSEPH MCGARRY
Smoke Detectors 12/31/2020 Approved JOSEPH MCGARRY