1608 N AMALFI DR 90272

Certificate Information: 1608 N AMALFI DR 90272

Application / Permit
19014-20000-03106
Plan Check / Job No.
B19VN09602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO AND (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 3/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 SELLA BENYAMIN
Corrections Issued 7/3/2019 SELLA BENYAMIN
Quality Review Completed 7/3/2019 STEVEN KIM
Building Plans Picked Up 7/3/2019 APPLICANT
Applicant returned to address corrections 1/31/2020 SELLA BENYAMIN
Plan Check Approved 3/10/2020 SELLA BENYAMIN
Issued 3/10/2020 LADBS
CofO in Progress 4/7/2023 KEVIN SARGSYAN
Permit Finaled 4/12/2023 DANIEL ORRANTE
CofO Issued 4/12/2023 DANIEL ORRANTE
Permit Finaled 4/12/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/9/2019 DENNIS BRAGIN
Miscellaneous Cleared 7/9/2019 TREVOR MARTIN
Miscellaneous Cleared 7/9/2019 TREVOR MARTIN
Sewer availability Cleared 7/9/2019 DENNIS BRAGIN
Green Code Cleared 9/3/2019 DAVID MATSON
Low Impact Development Cleared 1/24/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/29/2020 ANTHONY MAINEZ

Contact Information

Contractor Suarez Build Construction Inc; Lic. No.: 1032579-B 1116 BERKELEY DRIVE      MARINA DEL REY, CA 90292
Engineer Nguyen,, Quynh Anh; Lic. No.: C58592 12000 MIRANDA ST      VALLEY VILLAGE, CA 91607

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/1/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 5/1/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/18/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 5/26/2020 Partial Approval ROBERT SHELLY
Deputy Reinf. Concrete 5/28/2020 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 8/21/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 8/31/2020 Partial Approval TIM CHRISTENSEN
PLUMBING-Rough 9/4/2020 Partial Approval TIM CHRISTENSEN
Sewer 9/4/2020 Approved TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 10/2/2020 Conditional Approval TIM CHRISTENSEN
Green Building Rough 10/2/2020 Not Ready for Inspection TIM CHRISTENSEN
Structural Steel Frame 10/2/2020 Partial Approval TIM CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 10/9/2020 Partial Approval TIM CHRISTENSEN
Underground Mechanical 10/9/2020 Partial Approval TIM CHRISTENSEN
Reinforced Concrete Frame 10/27/2020 Conditional Approval TIM CHRISTENSEN
Footing/Foundation/Slab 10/28/2020 Partial Approval TIM CHRISTENSEN
Footing/Foundation/Slab 11/6/2020 Partial Approval MATT KELLERMAN
Special/Order Compliance 11/17/2020 Partial Inspection JOHN KIDWELL
Footing/Foundation/Slab 11/20/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 11/20/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 11/23/2020 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 11/25/2020 Approved ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 12/1/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 12/1/2020 Approved EVAN COOPER
Deputy Wood Construction 12/16/2020 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 4/1/2021 Corrections Issued ANDREW NAVE
Special/Order Compliance 5/4/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval JUAN VALENZUELA
HVAC-Rough 5/17/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 5/17/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 5/20/2021 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/7/2021 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Corrections Issued ANDREW NAVE
Green Building Rough 6/7/2021 Not Ready for Inspection ANDREW NAVE
Interior/Exterior Lathing 6/11/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 6/18/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 6/18/2021 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 6/18/2021 Partial Approval JUAN VALENZUELA
Wood Frame 6/18/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval JUAN VALENZUELA
Special/Order Compliance 7/6/2021 Partial Approval JUAN VALENZUELA
Insulation 7/16/2021 Partial Approval PIERRE VEGA
Shower Pan 8/5/2021 Approved KRISTEN CAUSEY
Drywall Nailing 8/6/2021 Partial Approval KRISTEN CAUSEY
Interior/Exterior Lathing 8/6/2021 Partial Approval KRISTEN CAUSEY
Pre-Inspection 3/22/2022 Partial Inspection JUAN VALENZUELA
Service/Power Release 3/22/2022 Not Ready for Inspection JUAN VALENZUELA
Gas Test 5/10/2022 Approved JUAN VALENZUELA
HVAC-Final 5/10/2022 Corrections Issued JUAN VALENZUELA
Service/Power Release 5/10/2022 Not Ready for Inspection JUAN VALENZUELA
Service/Power Release 5/12/2022 Approved JOHN KIDWELL
HVAC-Final 5/20/2022 Approved JUAN VALENZUELA
ELECTRICAL-Final 5/24/2022 Approved JUAN VALENZUELA
Structural Steel Frame 6/16/2022 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
Final 6/21/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Final 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 6/21/2022 Not Ready for Inspection JUAN VALENZUELA
Gas Test 9/8/2022 Approved JUAN VALENZUELA
PLUMBING-Final 9/19/2022 Conditional Approval JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 1/12/2023 SGSOV Not Ready BRENDAN LOONEY
PLUMBING-Final 3/6/2023 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 3/7/2023 Approved KEVIN SARGSYAN
Final 3/7/2023 Corrections Issued KEVIN SARGSYAN
Green Building Final 3/7/2023 Corrections Issued KEVIN SARGSYAN
Green Building Rough 3/7/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Not Ready KEVIN SARGSYAN
Smoke Detectors 3/7/2023 Approved KEVIN SARGSYAN
Structural Steel Frame 3/7/2023 Approved KEVIN SARGSYAN
Final 3/22/2023 Not Ready for Inspection KEVIN SARGSYAN
Green Building Final 3/22/2023 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Approved KEVIN SARGSYAN
Final 4/6/2023 OK to Issue CofO KEVIN SARGSYAN