4635 N LIBBIT AVE 91436

Certificate Information: 4635 N LIBBIT AVE 91436

Application / Permit
19014-20000-03082
Plan Check / Job No.
B19VN09507
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 44' 8" X 23' TO REAR, ADD 3' X 2' 7" TO FRONT, REMODEL 10' X 18' 8" AND REFRAME 16' 6" X 27' TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/7/2020
Issuing Office
Current Status
CofO Issued on 1/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Green Plans Picked Up 6/18/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 GURUNATH NESARAJAH
Corrections Issued 6/29/2019 GURUNATH NESARAJAH
Quality Review Completed 7/5/2019 OMID HEDAYAT
Building Plans Picked Up 7/8/2019 APPLICANT
Plan Check Approved 1/17/2020 GURUNATH NESARAJAH
Issued 10/7/2020 APPLICANT
CofO in Progress 8/11/2023 VINCENT HANLEY
Permit Finaled 1/19/2024 JOHN JANSON
CofO Issued 1/19/2024 JOHN JANSON
Permit Finaled 1/19/2024 JOHN JANSON

Permit Application Clearance Information

GPI Written Notices Cleared 12/18/2019 GURUNATH NESARAJAH
Grading Pre-Inspection Cleared 12/18/2019 GURUNATH NESARAJAH
Eng Process Fee Ord 176,300 Cleared 1/16/2020 GUILLERMO PETRA
Green Code Cleared 1/16/2020 DAVID MATSON
Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/16/2020 CELINA MORENO
Sewer availability Cleared 1/16/2020 GUILLERMO PETRA
ZA Case Cleared 1/17/2020 VINCENT QUITORIANO

Contact Information

Architect Dimster,, Don M; Lic. No.: C28076 623 VERNON AVE.      VENICE, CA 90291
Contractor Pineda Franklin Construction; Lic. No.: 874991-B 1862 EL SERENO AVENUE      PASADENA, CA 91103
Engineer Niaki,, Neman; Lic. No.: C46030 1107 CALIFORNIA AVE #2      SANTA MONICA, CA 90403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/29/2020 Approved RONALD COWAN
Deputy Drilled-In Anchors 11/17/2020 Approved RONALD COWAN
Footing/Foundation/Slab 11/20/2020 Partial Approval RONALD COWAN
Underground Mechanical 11/24/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 12/9/2020 Approved RONALD COWAN
PLUMBING-Rough 2/4/2021 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Partial Approval RONALD COWAN
HVAC-Rough 3/19/2021 Partial Approval RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 5/5/2021 Approved STEVEN BACK
ELECTRICAL-Rough 5/6/2021 Not Ready for Inspection TROY SANDERS
ELECTRICAL-Rough 6/15/2021 Approved RONALD COWAN
HVAC-Rough 6/15/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 7/14/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 7/14/2021 Corrections Issued RONALD COWAN
Shower Pan 7/22/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 8/9/2021 Approved RONALD COWAN
Green Building Rough 8/9/2021 Approved RONALD COWAN
Interior/Exterior Lathing 8/9/2021 Partial Approval RONALD COWAN
Insulation 8/16/2021 Corrections Issued RYAN SALAZAR
Insulation 8/20/2021 Approved RYAN SALAZAR
Drywall Nailing 9/7/2021 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/7/2021 Approved KRISTEN CAUSEY
HVAC-Rough 9/8/2021 Approved RONALD COWAN
Sewer 1/18/2022 Not Ready for Inspection JUSTIN HAWLEY
Sewer 1/20/2022 Approved JUSTIN HAWLEY
Gas Test 1/25/2022 Not Ready for Inspection JESUS PINEDA
Gas Test 1/28/2022 Approved JESUS PINEDA
ELECTRICAL-Final 2/15/2022 Approved VINCENT HANLEY
PLUMBING-Final 2/23/2022 Approved PETER FOLLING
HVAC-Final 3/4/2022 Approved VINCENT HANLEY
Final 5/20/2022 Corrections Issued PETER FOLLING
Green Building Final 5/20/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 5/20/2022 SGSOV Approved PETER FOLLING
Smoke Detectors 5/20/2022 Approved PETER FOLLING
Final 3/17/2023 Not Ready for Inspection VINCENT HANLEY
Final 8/10/2023 OK to Issue CofO VINCENT HANLEY
Special/Order Compliance 12/29/2023 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Approved VINCENT HANLEY