16529 W INDEX ST 91344

Certificate Information: 16529 W INDEX ST 91344

Application / Permit
19014-20000-03059
Plan Check / Job No.
B19VN09431
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD IRREGULAR SHAPE28'; X 20'5" TO DETACHED GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB494 & SB229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 6/11/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 ALDOUS CHIC
Corrections Issued 6/7/2019 ALDOUS CHIC
Plan Check Approved 6/11/2019 SAMUEL GONZALEZ
Issued 6/11/2019 LADBS
CofO in Progress 4/9/2021 MARK JOHNSON
CofO Issued 10/2/2021 MICHAEL SMITH
Permit Finaled 10/2/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/7/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 6/7/2019 GUILLERMO PETRA
Permit Cleared 6/7/2019 GUILLERMO PETRA
Sewer availability Cleared 6/7/2019 GUILLERMO PETRA
Grading Pre-Inspection Cleared 6/11/2019 ALDOUS CHIC
Low Impact Development Cleared 6/11/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 6/11/2019 APEKSHYA BAJRACHARYA
Trees in Parkway Cleared 6/11/2019 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2019 Partial Approval MARK JOHNSON
PLUMBING-Rough 8/30/2019 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 11/27/2019 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/27/2019 Corrections Issued MARK JOHNSON
Underground Mechanical 11/27/2019 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/24/2019 Not Ready for Inspection MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 12/24/2019 Partial Approval MARK JOHNSON
Green Building Rough 12/24/2019 Not Ready for Inspection MARK JOHNSON
MERV13>=Rough 12/24/2019 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 3/17/2020 Approved MARK JOHNSON
HVAC-Rough 4/14/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 4/14/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 4/16/2020 Not Ready for Inspection MARK JOHNSON
Green Building Rough 4/16/2020 Approved MARK JOHNSON
HVAC-Rough 4/16/2020 Approved MARK JOHNSON
MERV13>=Rough 4/16/2020 Approved MARK JOHNSON
PLUMBING-Rough 4/16/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 4/23/2020 Approved MARK JOHNSON
Drywall Nailing 4/23/2020 Not Ready for Inspection MARK JOHNSON
Final 4/23/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 4/23/2020 Approved MARK JOHNSON
Green Building Final 4/23/2020 Not Ready for Inspection MARK JOHNSON
MERV13>=Final 4/23/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 4/23/2020 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 4/23/2020 Not Ready for Inspection MARK JOHNSON
Insulation 4/24/2020 Approved MARK JOHNSON
Drywall Nailing 5/4/2020 Approved MARK JOHNSON
Final 5/15/2020 Not Ready for Inspection MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 5/15/2020 SGSOV Not Ready MARK JOHNSON
Shower Pan 5/15/2020 Approved MARK JOHNSON
Smoke Detectors 5/15/2020 Not Ready for Inspection MARK JOHNSON
Final 5/19/2020 Not Ready for Inspection MARK JOHNSON
Interior/Exterior Lathing 5/19/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 5/19/2020 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 5/19/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Final 6/18/2020 No Access for Inspection MARK JOHNSON
ELECTRICAL-Final 6/22/2020 Corrections Issued DANIEL DREW
Service/Power Release 6/26/2020 Approved WILLIAM KUEHN
Final 10/1/2020 Corrections Issued MARK JOHNSON
Green Building Final 10/1/2020 Not Ready for Inspection MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 10/1/2020 SGSOV Not Ready MARK JOHNSON
Smoke Detectors 10/1/2020 Not Ready for Inspection MARK JOHNSON
Special/Order Compliance 10/7/2020 Corrections Issued MICHAEL TEMPLE
ELECTRICAL-Final 4/9/2021 Approved MARK JOHNSON
Final 4/9/2021 OK to Issue CofO MARK JOHNSON
Green Building Final 4/9/2021 Approved MARK JOHNSON
HVAC-Final 4/9/2021 Approved MARK JOHNSON
PLUMBING-Final 4/9/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 4/9/2021 Approved MARK JOHNSON