4463 N CORONET DR 91316

Certificate Information: 4463 N CORONET DR 91316

Application / Permit
19014-20000-03030
Plan Check / Job No.
B19VN09350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
(N) 2nd floor addition, irregular shaped 31'x 34'-6" accessory living quarters to detached 2-car garage with storage/study at first floor. NFPA 13 D fire sprinklers required throughout
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
CofO in Progress on 9/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Green Plans Picked Up 7/16/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 ALYSSA N NARCISO
Corrections Issued 7/25/2019 ALYSSA N NARCISO
Quality Review Completed 7/26/2019 CHON CHIO KUO
Building Plans Picked Up 7/29/2019 APPLICANT
Applicant returned to address corrections 10/24/2019 ALYSSA N NARCISO
Applicant returned to address corrections 11/12/2019 ALYSSA N NARCISO
Plan Check Approved 11/25/2019 ALYSSA N NARCISO
Issued 2/19/2020 LADBS
CofO in Progress 9/27/2023 VINCENT HANLEY

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 8/1/2019 APEKSHYA BAJRACHARYA
BHO/Hillside ordinance Cleared 8/1/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 8/26/2019 MICHAEL AYERS
Eng Process Fee Ord 176,300 Cleared 9/16/2019 GABRIEL ROBLES
Sewer availability Cleared 9/16/2019 GABRIEL ROBLES
Low Impact Development Cleared 9/17/2019 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/18/2019 GABRIEL ROBLES
Fire Marshall Fire Life Safety Cleared 9/19/2019 GILBERT URREA
Hydrant and Access approval Cleared 9/19/2019 GILBERT URREA
BHO/Hillside ordinance Cleared 10/24/2019 APEKSHYA BAJRACHARYA
GPI Written Notices Cleared 10/24/2019 ALYSSA N NARCISO
Grading Pre-Inspection Cleared 10/24/2019 ALYSSA N NARCISO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/28/2020 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 9/24/2020 Partial Approval RONALD COWAN
Pre-Inspection 9/24/2020 Partial Approval RONALD COWAN
Footing/Foundation/Slab 10/7/2020 Approved RONALD COWAN
Wood Frame 10/23/2020 Partial Approval RONALD COWAN
ELECTRICAL-Rough 12/7/2020 Approved RONALD COWAN
PLUMBING-Rough 12/7/2020 Approved RONALD COWAN
Deputy Wood Construction 12/23/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Approval DAVID SANDOVAL
HVAC-Rough 1/4/2021 Corrections Issued DAVID SANDOVAL
BUILDING-Rough-Frame 1/15/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 1/15/2021 Not Ready for Inspection RONALD COWAN
HVAC-Rough 1/15/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 1/15/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 1/15/2021 Not Ready for Inspection RONALD COWAN
BUILDING-Rough-Frame 2/11/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Approved RONALD COWAN
Green Building Rough 2/11/2021 Approved RONALD COWAN
HVAC-Rough 2/11/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 2/11/2021 Approved RONALD COWAN
Wood Frame 2/11/2021 Approved RONALD COWAN
Insulation 2/17/2021 Not Ready for Inspection RONALD COWAN
Interior/Exterior Lathing 2/17/2021 Partial Approval RONALD COWAN
Deck 2/18/2021 Approved RONALD COWAN
Shower Pan 2/18/2021 Approved RONALD COWAN
Drywall Nailing 2/22/2021 Approved RONALD COWAN
Interior/Exterior Lathing 2/22/2021 Approved RONALD COWAN
PLUMBING-Rough 4/16/2021 Corrections Issued RONALD COWAN
Final 3/22/2022 Corrections Issued DAVID SANDOVAL
Green Building Final 3/22/2022 No Access for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Not Ready DAVID SANDOVAL
Smoke Detectors 3/22/2022 Approved DAVID SANDOVAL
ELECTRICAL-Final 3/29/2023 Approved VINCENT HANLEY
Final 3/29/2023 Corrections Issued VINCENT HANLEY
Green Building Final 3/29/2023 Approved VINCENT HANLEY
HVAC-Final 3/29/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Final 3/29/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/29/2023 SGSOV Approved VINCENT HANLEY
Final 9/13/2023 Corrections Issued VINCENT HANLEY
Service/Power Release 9/13/2023 Approved VINCENT HANLEY
Final 9/27/2023 OK to Issue CofO VINCENT HANLEY