6305 N RANCHITO AVE 91401

Certificate Information: 6305 N RANCHITO AVE 91401

Application / Permit
19014-20000-02999
Plan Check / Job No.
B19VN09271
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) (18'-2" X 20'-2") DETACHED GARAGE AND ADD (29'-9" X 40') IRREGULAR SHAPED TO CREATE (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/10/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2019 APPLICANT
Assigned to Plan Check Engineer 6/5/2019 ALDOUS CHIC
Corrections Issued 6/5/2019 ALDOUS CHIC
Plan Check Approved 7/1/2019 RAPHAEL ROSAS
Issued 7/10/2019 LADBS
CofO in Progress 9/15/2020 WILLIAM KUEHN
No Progress 11/9/2020 MICHAEL TEMPLE
CofO in Progress 3/19/2021 MICHAEL TEMPLE
CofO Issued 4/17/2021 MICHAEL SMITH
Permit Finaled 4/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/5/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 6/5/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 6/5/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 6/25/2019 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 6/26/2019 NADER ISKANDER
Roof/Waste drainage to street Cleared 6/26/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/1/2020 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 5/5/2020 Corrections Issued MISAEL ESPARZA
Underground Mechanical 5/5/2020 Partial Approval MISAEL ESPARZA
Deputy Drilled-In Anchors 5/6/2020 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/7/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/17/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 6/17/2020 Approved MATTHEW NELSON
Green Building Rough 6/17/2020 Approved MATTHEW NELSON
HVAC-Rough 6/17/2020 Approved MATTHEW NELSON
PLUMBING-Rough 6/17/2020 Approved MATTHEW NELSON
Wood Frame 6/17/2020 Approved MATTHEW NELSON
Insulation 6/22/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 6/22/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Partial Approval RAYMOND KEHOE
Shower Pan 6/24/2020 Approved RAYMOND KEHOE
Drywall Nailing 6/29/2020 Partial Approval MISAEL ESPARZA
Drywall Nailing 7/2/2020 Approved MISAEL ESPARZA
Underground Mechanical 7/22/2020 Partial Approval MATTHEW NELSON
Underground Mechanical 8/7/2020 Partial Inspection WILLIAM KUEHN
Final 9/4/2020 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 9/4/2020 Partial Inspection MICHEL ABAJAN
Green Building Final 9/4/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/4/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 9/4/2020 Approved MICHEL ABAJAN
Final 9/14/2020 OK to Issue CofO WILLIAM KUEHN
Footing/Foundation/Slab 9/14/2020 Approved WILLIAM KUEHN
Green Building Final 9/14/2020 Approved WILLIAM KUEHN
Special/Order Compliance 11/9/2020 Corrections Issued MICHAEL TEMPLE