3504 W LARGA AVE 90039

Certificate Information: 3504 W LARGA AVE 90039

Application / Permit
19014-20000-02991
Plan Check / Job No.
B19VN09224
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'-11" X 18'-11" TWO STORY ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER AB 494 AND SB 229. SEE COMMENTS.
Permit Issued
Issued on 8/6/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/4/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 JEROME MAGAT PALMA
Corrections Issued 6/24/2019 JEROME MAGAT PALMA
Quality Review Completed 6/24/2019 ABDUL CHEGENI
Building Plans Picked Up 6/24/2019 APPLICANT
Green Plans Picked Up 8/1/2019 APPLICANT
Plan Check Approved 8/6/2019 JEROME MAGAT PALMA
Issued 8/6/2019 LADBS
CofO in Progress 11/25/2020 HAMIK HARTOUNIAN
Permit Finaled 9/3/2021 DEROLD HAUFF
CofO Issued 9/3/2021 DEROLD HAUFF
Permit Finaled 9/3/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/6/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/6/2019 LEE GUILBEAUX
Green Code Cleared 8/6/2019 MICHAEL AYERS
Roof/Waste drainage to street Cleared 8/6/2019 LEE GUILBEAUX
Sewer availability Cleared 8/6/2019 LEE GUILBEAUX
ZI Cleared 8/6/2019 HERMINIGILDO AGUSTIN

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2020 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 3/3/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 3/24/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 3/24/2020 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/27/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 4/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 4/27/2020 Corrections Issued HAMIK HARTOUNIAN
Shower Pan 4/27/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/1/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/7/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/7/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 5/7/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/7/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/20/2020 Conditional Approval HAMIK HARTOUNIAN
Insulation 5/20/2020 Conditional Approval HAMIK HARTOUNIAN
Drywall Nailing 6/12/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/12/2020 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/10/2020 Approved HAMIK HARTOUNIAN
Final 11/10/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/10/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 11/10/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/10/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 11/10/2020 Approved HAMIK HARTOUNIAN
Final 11/24/2020 OK to Issue CofO HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/24/2020 SGSOV Approved HAMIK HARTOUNIAN