3504 W LARGA AVE 90039
Certificate Information: 3504 W LARGA AVE 90039
- Application / Permit
- 19014-20000-02991
- Plan Check / Job No.
- B19VN09224
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-11" X 18'-11" TWO STORY ACCESSORY DWELLING UNIT ADDITION TO (E) DETACHED GARAGE PER AB 494 AND SB 229. SEE COMMENTS.
- Permit Issued
- Issued on 8/6/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | JEROME MAGAT PALMA |
| Corrections Issued | 6/24/2019 | JEROME MAGAT PALMA |
| Quality Review Completed | 6/24/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/24/2019 | APPLICANT |
| Green Plans Picked Up | 8/1/2019 | APPLICANT |
| Plan Check Approved | 8/6/2019 | JEROME MAGAT PALMA |
| Issued | 8/6/2019 | LADBS |
| CofO in Progress | 11/25/2020 | HAMIK HARTOUNIAN |
| Permit Finaled | 9/3/2021 | DEROLD HAUFF |
| CofO Issued | 9/3/2021 | DEROLD HAUFF |
| Permit Finaled | 9/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 8/6/2019 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 8/6/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/6/2019 | LEE GUILBEAUX |
| ZI | Cleared | 8/6/2019 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2020 | Partial Inspection | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 3/3/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 3/24/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 3/24/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 4/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 4/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Rough | 4/27/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 4/27/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Shower Pan | 4/27/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 5/1/2020 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/7/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 5/7/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 5/7/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/7/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Insulation | 5/20/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 6/12/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/12/2020 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/10/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/10/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/10/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 11/10/2020 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/10/2020 | Approved | HAMIK HARTOUNIAN |
| Final | 11/24/2020 | OK to Issue CofO | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/24/2020 | SGSOV Approved | HAMIK HARTOUNIAN |