13830 W COLLINS ST 91401

Certificate Information: 13830 W COLLINS ST 91401

Application / Permit
19014-20000-02978
Plan Check / Job No.
B19VN09204
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Second Story ADDITION & CONVERT (E) detached Garage to an Accessory Dwelling Unit per AB 494 AND SB 229. Building to be a 25' x 25' two-story structure with 2 bedrooms, 2 full bathrooms, one half bathroom, and a kitchen/living room.
Permit Issued
Issued on 1/23/2020
Issuing Office
Valley
Current Status
Issued on 1/23/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 LUIS RINCON
Corrections Issued 7/13/2019 LUIS RINCON
Green Plans Picked Up 7/18/2019 APPLICANT
Quality Review Completed 7/22/2019 OMID HEDAYAT
Building Plans Picked Up 7/24/2019 APPLICANT
Plan Check Approved 1/17/2020 LUIS RINCON
Issued 1/23/2020 LADBS

Permit Application Clearance Information

Green Code Cleared 11/7/2019 PARISA ZAHABI
Permit Cleared 12/11/2019 ADRIAN CASTRO
Low Impact Development Cleared 12/20/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/23/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/2/2020 ADRIAN CASTRO
Address approval Cleared 1/9/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 1/9/2020 GEORGE SUCHAND
Sewer availability Cleared 1/9/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Abkarian,, Raffi; Lic. No.: C36027 18763 VINTAGE STREET      NORTHRIDGE, CA 91324

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/4/2020 Corrections Issued MISAEL ESPARZA
Underground Mechanical 6/4/2020 Not Ready for Inspection MISAEL ESPARZA
Posting Pre-Inspection 11/25/2020 Approved WILLIAM KUEHN
Underground Mechanical 11/25/2020 Partial Inspection WILLIAM KUEHN
Footing/Foundation/Slab 4/13/2021 Not Ready for Inspection MICHAEL TEMPLE
Footing/Foundation/Slab 6/10/2021 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 6/15/2021 Approved MISAEL ESPARZA
PLUMBING-Rough 6/15/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/10/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 1/28/2022 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 1/28/2022 Not Ready for Inspection RICHARD DOCKUS
PLUMBING-Rough 1/28/2022 Not Ready for Inspection RICHARD DOCKUS
Wood Frame 1/28/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 2/7/2022 Partial Approval RICHARD DOCKUS
Green Building Rough 2/7/2022 Approved RICHARD DOCKUS
HVAC-Rough 2/7/2022 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 2/7/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 3/15/2022 Approved KRISTEN CAUSEY
Shower Pan 3/15/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 4/4/2022 Corrections Issued RICHARD DOCKUS
BUILDING-Rough-Frame 4/11/2022 Approved RICHARD DOCKUS
HVAC-Rough 4/11/2022 Approved RICHARD DOCKUS
Underground Mechanical 11/22/2022 Partial Approval MICHEL ABAJAN
Underground Mechanical 2/6/2023 Not Ready for Inspection JOHN COLEMAN
Underground Mechanical 2/7/2023 Partial Approval THOMAS FINNILA
Underground Mechanical 2/8/2023 Approved THOMAS FINNILA
Special/Order Compliance 11/10/2025 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 12/10/2025 Partial Inspection JOAQUIN GREENOUGH