15533 W COHASSET ST 91406

Certificate Information: 15533 W COHASSET ST 91406

Application / Permit
19014-20000-02870
Plan Check / Job No.
B19VN08915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (22'-3" X 26'-11") IRREGULAR SHAPE ADDITION TO (E) SFD FOR (N) BEDROOMS AND BATHROOM.
Permit Issued
Issued on 7/3/2019
Issuing Office
Valley
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 RAPHAEL ROSAS
Corrections Issued 5/30/2019 RAPHAEL ROSAS
Applicant returned to address corrections 6/28/2019 RAPHAEL ROSAS
Plan Check Approved 7/2/2019 PINANK PATEL
Issued 7/3/2019 LADBS
CofO in Progress 2/8/2024 GREGG CUMMINGS
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 5/30/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/2/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 7/2/2019 APEKSHYA BAJRACHARYA

Contact Information

Architect Reyes,, Zinayda; Lic. No.: C36177 1409 N HAVENHURST DRIVE # 3      WEST HOLLYWOOD, CA 90046
Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/2/2020 Corrections Issued WILLIAM KUEHN
Footing/Foundation/Slab 3/2/2020 Not Ready for Inspection WILLIAM KUEHN
Footing/Foundation/Slab 7/31/2020 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/4/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 9/18/2020 Corrections Issued JENNIFER RABUCHIN
Insulation 9/18/2020 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/18/2020 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/25/2022 Partial Approval GREGG CUMMINGS
Green Building Rough 3/25/2022 Not Ready for Inspection GREGG CUMMINGS
Insulation 3/25/2022 Corrections Issued GREGG CUMMINGS
Service/Power Release 3/25/2022 Not Ready for Inspection GREGG CUMMINGS
Insulation 4/14/2022 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 6/1/2022 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 6/1/2022 Not Ready for Inspection GREGG CUMMINGS
MERV13>=Rough 6/1/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 10/17/2022 Approved GREGG CUMMINGS
Green Building Rough 10/17/2022 Approved GREGG CUMMINGS
HVAC-Rough 10/17/2022 Corrections Issued GREGG CUMMINGS
MERV13>=Rough 10/17/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 10/17/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 1/24/2023 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 1/24/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 1/24/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 2/16/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/6/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 4/10/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/10/2023 Approved CHRISTOPHER DELLEFIELD
Final 11/6/2023 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 11/6/2023 Approved MISAEL ESPARZA
Green Building Final 11/6/2023 Not Ready for Inspection MISAEL ESPARZA
MERV13>=Final 11/6/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 11/6/2023 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 11/6/2023 Corrections Issued MISAEL ESPARZA
Final 2/1/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Final 2/1/2024 Approved GREGG CUMMINGS
Smoke Detectors 2/1/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/7/2024 Approved GREGG CUMMINGS
Final 2/7/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 2/7/2024 Approved GREGG CUMMINGS
PLUMBING-Final 2/7/2024 Approved GREGG CUMMINGS