3103 S BENTLEY AVE 90034
Certificate Information: 3103 S BENTLEY AVE 90034
- Application / Permit
- 19014-20000-02800
- Plan Check / Job No.
- B19VN08702
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 19'-0" X 13'-0" SECOND FLOOR ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT AB 494 AND SB 229
- Permit Issued
- Issued on 6/5/2020
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | JEROME MAGAT PALMA |
| Green Plans Picked Up | 6/13/2019 | APPLICANT |
| Corrections Issued | 6/17/2019 | JEROME MAGAT PALMA |
| Quality Review Completed | 6/18/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/19/2019 | APPLICANT |
| Plan Check Approved | 7/29/2019 | JEROME MAGAT PALMA |
| No Progress | 7/29/2019 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/3/2019 | JEROME MAGAT PALMA |
| Issued | 6/5/2020 | APPLICANT |
| Permit Finaled | 4/22/2025 | RICHARD STEINBACH |
| CofO Issued | 4/22/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/22/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 7/24/2019 | LEE GUILBEAUX |
| Green Code | Cleared | 7/26/2019 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 7/29/2019 | JEROME MAGAT PALMA |
| Construction near power lines | Cleared | 10/3/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/13/2020 | Partial Approval | EVAN COOPER |
| Underground Mechanical | 8/13/2020 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 8/21/2020 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2020 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/15/2020 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/5/2020 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/5/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Approved | JOHNNY MIRANDA |
| Gas Test | 10/5/2020 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 10/5/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 10/5/2020 | Corrections Issued | JOHNNY MIRANDA |
| MERV13>=Rough | 10/5/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/5/2020 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 10/9/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/9/2020 | Approved | EVAN COOPER |
| Gas Test | 10/9/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 10/9/2020 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 10/9/2020 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/9/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/22/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 10/22/2020 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 10/22/2020 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 11/5/2020 | Approved | EVAN COOPER |
| Green Building Rough | 11/5/2020 | Approved | EVAN COOPER |
| Insulation | 11/5/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/5/2020 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 11/12/2020 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/23/2020 | Corrections Issued | RICHARD ROBLES |
| Service/Power Release | 12/29/2020 | Partial Inspection | OGANES TARAKHCHYAN |
| Gas Test | 1/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Sewer | 1/12/2021 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 1/15/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/9/2021 | Corrections Issued | RICHARD ROBLES |
| Final | 3/9/2021 | Corrections Issued | RICHARD ROBLES |
| Green Building Final | 3/9/2021 | Corrections Issued | RICHARD ROBLES |
| MERV13>=Final | 3/9/2021 | Approved | RICHARD ROBLES |
| SGSOV-Seismic Gas S/O Valve | 3/9/2021 | SGSOV Not Ready | RICHARD ROBLES |
| Smoke Detectors | 3/9/2021 | Corrections Issued | RICHARD ROBLES |
| Final | 3/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/18/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/18/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 3/24/2021 | Corrections Issued | KENNETH NAGLE |
| Green Building Final | 3/24/2021 | Corrections Issued | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 3/24/2021 | SGSOV Approved | KENNETH NAGLE |
| Smoke Detectors | 3/24/2021 | Corrections Issued | KENNETH NAGLE |
| Final | 4/1/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 4/1/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 4/1/2021 | Conditional Approval | EVAN COOPER |
| Final | 4/14/2021 | Conditional Approval | EVAN COOPER |
| Service/Power Release | 4/14/2021 | Approved | EVAN COOPER |
| Smoke Detectors | 4/14/2021 | Approved | EVAN COOPER |