17808 W LEMARSH ST 91325

Certificate Information: 17808 W LEMARSH ST 91325

Application / Permit
19014-20000-02732
Plan Check / Job No.
B19VN08495
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION / REMODEL TO (E) SFD
Permit Issued
Issued on 6/26/2023
Issuing Office
Valley
Current Status
CofO in Progress on 4/2/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 YAQUB MIRZA
Corrections Issued 5/23/2019 YAQUB MIRZA
Building Plans Picked Up 6/13/2019 APPLICANT
Plan Check Approved 9/10/2019 YAQUB MIRZA
Issued 6/26/2023 APPLICANT
CofO in Progress 4/2/2026 CHRISTOPHER ROJAS
CofO in Progress 4/21/2026 JOSE AVILA
CofO in Progress 5/19/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/6/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 8/6/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 8/27/2019 RYAN HUDSON
Roof/Waste drainage to street Cleared 8/27/2019 JOHN LIN

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Gomez E Construction; Lic. No.: 1024152-B 17736 LEMARSH ST      NORTHRIDGE, CA 91325

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/10/2024 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 12/18/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/26/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 1/30/2025 Partial Approval JAVIER RAMOS JR
Insulation 1/30/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/30/2025 Partial Approval JAVIER RAMOS JR
Deputy Wood Construction 2/4/2025 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 3/12/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/12/2025 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 3/12/2025 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 4/18/2025 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 4/22/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 4/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 4/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/30/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 4/30/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 4/30/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 4/30/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 4/30/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/7/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 5/7/2025 Approved CHRISTOPHER ROJAS
Insulation 5/7/2025 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 5/7/2025 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/12/2025 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 5/12/2025 Approved CHRISTOPHER ROJAS
Insulation 5/12/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/12/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 5/12/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/14/2025 Approved CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 5/14/2025 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 5/14/2025 Approved CHRISTOPHER ROJAS
Insulation 5/14/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 5/14/2025 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 5/14/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 5/22/2025 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 7/14/2025 Approved MICHAEL CORTEZ
Shower Pan 7/21/2025 Corrections Issued NICHOLAS TROWBRIDGE
Shower Pan 7/28/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Shower Pan 8/1/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/26/2025 Corrections Issued NICHOLAS TROWBRIDGE
Pre-Inspection 9/9/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 11/20/2025 Corrections Issued CHRISTOPHER ROJAS
Final 11/20/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/20/2025 Approved CHRISTOPHER ROJAS
Green Building Final 11/20/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 11/20/2025 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/20/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 11/20/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/27/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/27/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 3/27/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 3/27/2026 Approved CHRISTOPHER ROJAS
PLUMBING-Final 3/27/2026 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/27/2026 SGSOV Approved CHRISTOPHER ROJAS
Final 4/2/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Special/Order Compliance 4/21/2026 Corrections Issued CHRISTOPHER ROJAS
Final 5/19/2026 OK to Issue CofO CHRISTOPHER ROJAS