17808 W LEMARSH ST 91325
Certificate Information: 17808 W LEMARSH ST 91325
- Application / Permit
- 19014-20000-02732
- Plan Check / Job No.
- B19VN08495
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION / REMODEL TO (E) SFD
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Valley
- Current Status
- CofO in Progress on 4/2/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | YAQUB MIRZA |
| Corrections Issued | 5/23/2019 | YAQUB MIRZA |
| Building Plans Picked Up | 6/13/2019 | APPLICANT |
| Plan Check Approved | 9/10/2019 | YAQUB MIRZA |
| Issued | 6/26/2023 | APPLICANT |
| CofO in Progress | 4/2/2026 | CHRISTOPHER ROJAS |
| CofO in Progress | 4/21/2026 | JOSE AVILA |
| CofO in Progress | 5/19/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 8/6/2019 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 8/27/2019 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 8/27/2019 | JOHN LIN |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Gomez E Construction; Lic. No.: 1024152-B | 17736 LEMARSH ST NORTHRIDGE, CA 91325 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/10/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Drilled-In Anchors | 12/18/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 12/26/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 1/30/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 2/4/2025 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 3/12/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/12/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2025 | Corrections Issued | JAVIER RAMOS JR |
| Deputy Wood Construction | 4/18/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/22/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 4/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Rough-Elec/Plmb/HVAC | 4/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 4/30/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 4/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 5/7/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/7/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/12/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 5/12/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/12/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/12/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/12/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 5/14/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Drilled-In Anchors | 5/14/2025 | Conditional Approval | RAUL OLAGI |
| ELECTRICAL-Rough | 5/14/2025 | Approved | CHRISTOPHER ROJAS |
| Insulation | 5/14/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 5/14/2025 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 5/14/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 5/22/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 7/14/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/21/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Shower Pan | 7/28/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Shower Pan | 8/1/2025 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/26/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Pre-Inspection | 9/9/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 11/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 11/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 11/20/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 11/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/20/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/20/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/27/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/27/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/27/2026 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 4/2/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Special/Order Compliance | 4/21/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 5/19/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |