23035 W STRATHERN ST 91304
Certificate Information: 23035 W STRATHERN ST 91304
- Application / Permit
- 19014-20000-02709
- Plan Check / Job No.
- B19VN08447
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAINTAIN (21'-11" LF) PORTIONOF (E) WALL & FOOTING @ WEST GARAGE WALL OF (E) SFD AND BUILT A (N) 2-STORY IRR. SHAPE (44'-6"x 56'-6"). MAJOR REMODEL TO (E) SFD. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/16/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2019 | APPLICANT |
| Green Plans Picked Up | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2019 | TROY DEGUZMAN |
| Corrections Issued | 7/10/2019 | TROY DEGUZMAN |
| Quality Review Completed | 7/10/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 7/12/2019 | APPLICANT |
| Plan Check Approved | 9/13/2019 | TROY DEGUZMAN |
| Issued | 9/16/2019 | LADBS |
| CofO in Progress | 4/20/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 4/20/2023 | JOHN JANSON |
| CofO Issued | 4/20/2023 | JOHN JANSON |
| Permit Finaled | 4/20/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 7/25/2019 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 7/29/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 8/6/2019 | ANDRES COVARRUBIAS |
| Green Code | Cleared | 8/8/2019 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | JOHN LIN |
Contact Information
| Contractor | Homme Electric Inc; Lic. No.: 798120-C10 | 4924 BALBOA BLVD #483 ENCINO, CA 91316 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/31/2019 | Partial Approval | PETER FOLLING |
| Excavation/Setback/Form/Re-Bar | 11/14/2019 | Approved | PETER FOLLING |
| Footing/Foundation/Slab | 11/14/2019 | Approved | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 12/18/2019 | Partial Approval | PETER FOLLING |
| Green Building Rough | 12/18/2019 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2020 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 2/25/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Green Building Rough | 2/25/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 2/25/2020 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Rough | 2/28/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Sewer | 2/28/2020 | Approved | DAVID STEPANYAN |
| Deputy Wood Construction | 3/2/2020 | Partial Approval | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Corrections Issued | MICHAEL TEMPLE |
| Green Building Rough | 3/5/2020 | Not Ready for Inspection | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/5/2020 | Corrections Issued | MICHAEL TEMPLE |
| PLUMBING-Rough | 3/16/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 3/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2020 | Partial Approval | DAVID STEPANYAN |
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 3/27/2020 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 3/27/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 5/26/2020 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/9/2020 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/9/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/9/2020 | Not Ready for Inspection | DAVID STEPANYAN |
| PLUMBING-Rough | 6/9/2020 | Approved | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 6/24/2020 | Approved | DAVID STEPANYAN |
| Green Building Rough | 6/24/2020 | Approved | DAVID STEPANYAN |
| HVAC-Rough | 6/24/2020 | Approved | DAVID STEPANYAN |
| Insulation | 8/19/2020 | Approved | DAVID STEPANYAN |
| Drywall Nailing | 10/5/2020 | Approved | DAVID STEPANYAN |
| Shower Pan | 11/17/2020 | Approved | DAVID STEPANYAN |
| Interior/Exterior Lathing | 11/24/2020 | Approved | DAVID STEPANYAN |
| Underground Mechanical | 4/20/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 2/27/2023 | Partial Inspection | JESUS PINEDA |
| ELECTRICAL-Final | 3/23/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 3/23/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 3/23/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 3/23/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/23/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 3/23/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 3/23/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 4/19/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 4/19/2023 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 4/19/2023 | Approved | CHRIS CHRISTENSEN |