913 N VISTA ST 90046
Certificate Information: 913 N VISTA ST 90046
- Application / Permit
- 19014-20000-02704
- Plan Check / Job No.
- B19VN08419
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Carport
- Work Description
- 18' X 20'6" ADDITION OF BEDROOM AND WALK IN CLOSET TO THE (E) SFD AND ADD A NEW 8'6" X 33' CARPORT.
- Permit Issued
- Issued on 5/22/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2019 | PINANK PATEL |
| Corrections Issued | 5/22/2019 | PINANK PATEL |
| Plan Check Approved | 5/22/2019 | PINANK PATEL |
| Issued | 5/22/2019 | LADBS |
| CofO in Progress | 10/16/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/19/2020 | DEROLD HAUFF |
| CofO Issued | 10/19/2020 | DEROLD HAUFF |
| Permit Finaled | 10/19/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 5/22/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 5/22/2019 | MARKOS PEREZ-BRAN |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | Accelerate Construction Inc; Lic. No.: 864438-B | 5348 OVERING DRIVE WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 6/8/2020 | Partial Approval | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 6/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 7/1/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 7/30/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 7/30/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/7/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 8/7/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 8/12/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 8/12/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 8/14/2020 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 8/20/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 8/20/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 9/9/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 10/15/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 10/15/2020 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 10/15/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 10/15/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 10/15/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/15/2020 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/15/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/15/2020 | Approved | CHRIS CHRISTENSEN |