651 E 95TH ST 90002

Certificate Information: 651 E 95TH ST 90002

Application / Permit
19014-20000-02694
Plan Check / Job No.
B19VN08393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION OF ADU PER AB494 AND SB229 ATTACHED TO EXISTING GARAGE.
Permit Issued
Issued on 5/6/2020
Issuing Office
Current Status
CofO Issued on 2/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2019 APPLICANT
Assigned to Plan Check Engineer 5/22/2019 SAMUEL GONZALEZ
Corrections Issued 5/22/2019 SAMUEL GONZALEZ
Building Plans Picked Up 5/24/2019 APPLICANT
Plan Check Approved 4/7/2020 SAMUEL GONZALEZ
Issued 5/6/2020 APPLICANT
CofO in Progress 12/23/2020 DAVID FEILER
Permit Finaled 2/6/2021 DEROLD HAUFF
CofO Issued 2/6/2021 DEROLD HAUFF
Permit Finaled 2/6/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/24/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 7/18/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 7/18/2019 GUILLERMO PETRA
Sewer availability Cleared 7/18/2019 GUILLERMO PETRA
Construction near power lines Cleared 3/10/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/13/2020 Partial Approval EUGENE CASSIDY
Footing/Foundation/Slab 5/13/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 5/13/2020 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 5/18/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/3/2020 Not Ready for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Approved BRIAN CHRISTIAN
Green Building Rough 6/3/2020 Not Ready for Inspection BRIAN CHRISTIAN
Wood Frame 6/3/2020 Not Ready for Inspection BRIAN CHRISTIAN
BUILDING-Rough-Frame 7/6/2020 Corrections Issued EUGENE CASSIDY
Gas Test 7/6/2020 Approved EUGENE CASSIDY
Green Building Rough 7/6/2020 Not Ready for Inspection EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/6/2020 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 7/16/2020 Approved EUGENE CASSIDY
Green Building Rough 7/16/2020 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 7/16/2020 Approved EUGENE CASSIDY
Insulation 7/22/2020 Approved EUGENE CASSIDY
Drywall Nailing 7/29/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 7/29/2020 Approved EUGENE CASSIDY
Gas Test 8/7/2020 Approved EUGENE CASSIDY
Sewer 8/7/2020 Corrections Issued EUGENE CASSIDY
Sewer 9/1/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
Final 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 11/9/2020 Approved EUGENE CASSIDY
Green Building Final 11/9/2020 Corrections Issued EUGENE CASSIDY
HVAC-Final 11/9/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/9/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 11/9/2020 Approved EUGENE CASSIDY
Final 12/9/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 12/9/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 12/9/2020 SGSOV Approved EUGENE CASSIDY
Final 12/21/2020 OK to Issue CofO DAVID FEILER
Service/Power Release 12/21/2020 Approved DAVID FEILER