6906 N AURA AVE 91335

Certificate Information: 6906 N AURA AVE 91335

Application / Permit
19014-20000-02671
Plan Check / Job No.
B19VN08296
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-11" X 20'-1" IRR. SHAPE ADDITION OF A MASTER BEDROOM AND BATHROOM AT THE SOUTHEAST CORNER OF THE (E) SFD.
Permit Issued
Issued on 9/29/2021
Issuing Office
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 5/21/2019 JEROME MAGAT PALMA
Corrections Issued 5/21/2019 JEROME MAGAT PALMA
Plan Check Approved 5/21/2019 PINANK PATEL
Issued 9/29/2021 APPLICANT
CofO in Progress 8/8/2022 JEFFREY BULL
Permit Finaled 8/29/2022 JOHN JANSON
CofO Issued 8/29/2022 JOHN JANSON
Permit Finaled 8/29/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/21/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 5/21/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 5/21/2019 MARKOS PEREZ-BRAN

Contact Information

Contractor Ellsworth Construction Inc; Lic. No.: 440939-B 4874 PALO DRIVE      TARZANA, CA 91356
Engineer Chou,, Shen-Sheng Albert; Lic. No.: S2516 3024 APTOS AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/18/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/20/2022 Partial Approval VINCENT HANLEY
Sewer 1/20/2022 Approved VINCENT HANLEY
Underground Mechanical 1/20/2022 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 1/24/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 1/25/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/25/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 3/16/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/16/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/16/2022 Approved VINCENT HANLEY
Green Building Rough 3/16/2022 Approved VINCENT HANLEY
HVAC-Rough 3/16/2022 Approved VINCENT HANLEY
PLUMBING-Rough 3/16/2022 Approved VINCENT HANLEY
Insulation 4/7/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 4/7/2022 Approved MORRIS JACKSON
Shower Pan 4/7/2022 Approved MORRIS JACKSON
Drywall Nailing 4/13/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 4/21/2022 Partial Approval VINCENT HANLEY
Final 7/13/2022 No Access for Inspection JEFFREY BULL
Green Building Final 7/13/2022 No Access for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/13/2022 No Access for Inspection JEFFREY BULL
Smoke Detectors 7/13/2022 No Access for Inspection JEFFREY BULL
Final 7/21/2022 Corrections Issued JEFFREY BULL
Green Building Final 7/21/2022 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Not Ready JEFFREY BULL
Smoke Detectors 7/21/2022 Approved JEFFREY BULL
Final 8/5/2022 OK to Issue CofO JEFFREY BULL
Green Building Final 8/5/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved JEFFREY BULL