464 N SWEETZER AVE 90048

Certificate Information: 464 N SWEETZER AVE 90048

Application / Permit
19014-20000-02638
Plan Check / Job No.
B19VN08184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 36'-10" X 29'-3" IRREGULAR SHAPED ADDITION TO RELOCATE AND REMODEL KITCHEN, FAMILY ROOM , DINING ROOM AND CREATE NEW BATHROOM AND INTERIOR REMODEL TO THE (E) SFD TO REMODEL (2) BEDROOMS , (2) BATHROOMS , CREATE (2) NEW BEDROOMS , MASTER BATHROOM , POWDER ROOM , ALL WORK PER ENGINEERING
Permit Issued
Issued on 7/26/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2019 APPLICANT
Assigned to Plan Check Engineer 5/17/2019 MARVEL DELACRUZ
Corrections Issued 5/17/2019 MARVEL DELACRUZ
Plan Check Approved 7/26/2019 RARES BODEA
Issued 7/26/2019 LADBS
CofO in Progress 2/9/2021 CHRIS CHRISTENSEN
Permit Finaled 6/3/2021 DEROLD HAUFF
CofO Issued 6/3/2021 DEROLD HAUFF
Permit Finaled 6/3/2021 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 7/3/2019 RINA LARA
Eng Process Fee Ord 176,300 Cleared 7/8/2019 JOHN LIN
Sewer availability Cleared 7/8/2019 JOHN LIN
Low Impact Development Cleared 7/26/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/26/2019 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2020 Approved RAUL BARAJAS
METHANE-Barrier 4/7/2020 Approved RAUL BARAJAS
METHANE-Subgrade 4/7/2020 Approved RAUL BARAJAS
Deputy Reinf. Concrete 4/8/2020 No Access for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/17/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 4/17/2020 Partial Inspection CHRIS CHRISTENSEN
METHANE-Rough 4/17/2020 Partial Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 4/17/2020 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 5/1/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/11/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/11/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 6/11/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/11/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 6/17/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/23/2020 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 6/25/2020 Approved CHRIS CHRISTENSEN
Wood Frame 6/25/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/6/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 7/6/2020 Approved THOMAS LOGRASSO
Service/Power Release 10/5/2020 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 12/3/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 12/3/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 12/24/2020 Corrections Issued CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/8/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 2/8/2021 Approved CHRIS CHRISTENSEN
Final 2/8/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 2/8/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 2/8/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 2/8/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 2/8/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 2/8/2021 Approved CHRIS CHRISTENSEN
Special/Order Compliance 5/24/2021 Corrections Issued CHRIS CHRISTENSEN