11166 W VALLEY SPRING LANE 91602

Certificate Information: 11166 W VALLEY SPRING LANE 91602

Application / Permit
19014-20000-02616
Plan Check / Job No.
B19VN08150
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) 1-STORY SFD W/ 22'-0" LF AND 11'-6" LF WALLS TO REMAIN, ADD IRREGULAR 80’-0” X 89'-0" 1-STORY SFD W/ ATTACHED 20'-11" X 36’-11” 3-CAR GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/20/2019
Issuing Office
Valley
Current Status
CofO Issued on 5/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2019 APPLICANT
Green Plans Picked Up 5/29/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 JENNIFER LEE
Corrections Issued 6/5/2019 JENNIFER LEE
Quality Review Completed 6/5/2019 STEVEN KIM
Building Plans Picked Up 6/6/2019 APPLICANT
Plan Check Approved 8/13/2019 JENNIFER LEE
Issued 8/20/2019 LADBS
CofO in Progress 5/3/2021 DANIEL DREW
Permit Finaled 5/14/2021 MICHAEL SMITH
CofO Issued 5/14/2021 MICHAEL SMITH
Permit Finaled 5/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Trees in Parkway Cleared 7/5/2019 HECTOR BANUELOS
Eng Process Fee Ord 176,300 Cleared 7/10/2019 SAFA JAVANMARDI
Permit Cleared 7/10/2019 SAFA JAVANMARDI
Sewer availability Cleared 7/10/2019 SAFA JAVANMARDI
Green Code Cleared 8/1/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 8/1/2019 GEORGE SUCHAND
Low Impact Development Cleared 8/2/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/9/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/2/2019 Corrections Issued JEFFREY PARD
Footing/Foundation/Slab 11/8/2019 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Approved JEFFREY PARD
ELECTRICAL-Rough 1/30/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 2/10/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 2/20/2020 Approved JEFFREY PARD
Masonry Wall/Backfill 2/20/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 3/3/2020 Corrections Issued JEFFREY PARD
PLUMBING-Rough 3/3/2020 Approved JEFFREY PARD
PLUMBING-Rough 3/5/2020 Approved JEFFREY PARD
Drywall Nailing 3/11/2020 Not Ready for Inspection JEFFREY PARD
Green Building Rough 3/11/2020 Approved JEFFREY PARD
Drywall Nailing 3/13/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 3/13/2020 Approved JEFFREY PARD
ELECTRICAL-Final 9/22/2020 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 10/5/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 12/8/2020 Conditional Approval THOMAS FINNILA
Final 12/8/2020 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 12/15/2020 Approved THOMAS FINNILA
Final 12/15/2020 Not Ready for Inspection THOMAS FINNILA
MERV13>=Rough 12/15/2020 Approved THOMAS FINNILA
Final 12/24/2020 No Access for Inspection THOMAS FINNILA
Green Building Final 12/24/2020 No Access for Inspection THOMAS FINNILA
MERV13>=Final 12/24/2020 No Access for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/24/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 12/24/2020 No Access for Inspection THOMAS FINNILA
MERV13>=Final 1/5/2021 Partial Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/12/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 1/12/2021 Approved THOMAS FINNILA
Green Building Final 2/19/2021 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 3/25/2021 Not Ready for Inspection DAVID SANDOVAL
Final 4/19/2021 Not Ready for Inspection THOMAS FINNILA
MERV13>=Final 4/19/2021 Approved THOMAS FINNILA
Final 4/30/2021 OK to Issue CofO DANIEL DREW
Green Building Final 4/30/2021 Approved DANIEL DREW
HVAC-Final 4/30/2021 Approved DANIEL DREW
PLUMBING-Final 4/30/2021 Approved DANIEL DREW