15921 W ROYAL OAK ROAD 91436
Certificate Information: 15921 W ROYAL OAK ROAD 91436
- Application / Permit
- 19014-20000-02598
- Plan Check / Job No.
- B19VN08086
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 17'7" X 34'6" IRR. SHAPE OF GROUND FLOOR AND 64'11" X 17'7" IRR. SHAPE ADDITION AND REMODEL TO (E) SFD W/ ATTACHED GARAGE. ALL WORK PER ENGINEER.
- Permit Issued
- Issued on 10/22/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | PINANK PATEL |
| Green Plans Picked Up | 5/31/2019 | APPLICANT |
| Corrections Issued | 6/3/2019 | PINANK PATEL |
| Quality Review Completed | 6/5/2019 | STEVEN KIM |
| Building Plans Picked Up | 6/6/2019 | APPLICANT |
| Plan Check Approved | 10/22/2019 | PINANK PATEL |
| Issued | 10/22/2019 | LADBS |
| CofO in Progress | 4/1/2021 | RONALD COWAN |
| Permit Finaled | 5/29/2021 | MICHAEL SMITH |
| CofO Issued | 5/29/2021 | MICHAEL SMITH |
| Permit Finaled | 5/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/3/2019 | PINANK PATEL |
| BHO/Hillside ordinance | Cleared | 6/18/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 6/18/2019 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 6/18/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/18/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 7/3/2019 | DAVID MATSON |
| Low Impact Development | Cleared | 7/3/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/3/2019 | JEANETTE VONG |
| GPI Written Notices | Cleared | 7/9/2019 | PINANK PATEL |
| Miscellaneous | Cleared | 10/22/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fernandez,, Agapito B; Lic. No.: C56546 | 7400 E SLAUSON AVE STE S COMMERCE, CA 90040 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/21/2019 | Corrections Issued | RONALD COWAN |
| Deputy Steel/Welding | 11/27/2019 | Approved | RONALD COWAN |
| Underground Mechanical | 1/10/2020 | Partial Approval | RONALD COWAN |
| BUILDING-Rough-Frame | 1/13/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2020 | Partial Approval | RONALD COWAN |
| Green Building Rough | 1/13/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2020 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 4/7/2020 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 4/7/2020 | Approved | RONALD COWAN |
| Green Building Rough | 4/7/2020 | Approved | RONALD COWAN |
| HVAC-Rough | 4/7/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/7/2020 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 4/7/2020 | Approved | RONALD COWAN |
| Insulation | 4/16/2020 | Approved | RONALD COWAN |
| Shower Pan | 4/16/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 4/23/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 5/5/2020 | Approved | RONALD COWAN |
| Final | 12/22/2020 | Not Ready for Inspection | PAUL CHOPP |
| Footing/Foundation/Slab | 12/22/2020 | Approved | PAUL CHOPP |
| Green Building Final | 12/22/2020 | Not Ready for Inspection | PAUL CHOPP |
| SGSOV-Seismic Gas S/O Valve | 12/22/2020 | SGSOV Not Ready | PAUL CHOPP |
| Smoke Detectors | 12/22/2020 | Not Ready for Inspection | PAUL CHOPP |
| ELECTRICAL-Final | 2/10/2021 | Partial Approval | RONALD COWAN |
| Final | 2/10/2021 | Not Ready for Inspection | RONALD COWAN |
| Green Building Final | 2/10/2021 | Approved | RONALD COWAN |
| HVAC-Final | 2/10/2021 | Approved | RONALD COWAN |
| PLUMBING-Final | 2/10/2021 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 2/10/2021 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 2/10/2021 | Not Ready for Inspection | RONALD COWAN |
| Final | 3/18/2021 | Corrections Issued | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Approved | RONALD COWAN |
| Smoke Detectors | 3/18/2021 | Approved | RONALD COWAN |
| Final | 3/31/2021 | OK to Issue CofO | RONALD COWAN |
| Special/Order Compliance | 4/27/2021 | Partial Inspection | MICHAEL PELHAM |