3256 S FAY AVE 90034
Certificate Information: 3256 S FAY AVE 90034
- Application / Permit
- 19014-20000-02539
- Plan Check / Job No.
- B19VN07883
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove all except 16' North side wall and footing, rebuild irregular shape 56'4" x 26' NFPA13D fire sprinkler througout 2-story dwelling with roof deck per design
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Green Plans Picked Up | 5/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | ALDOUS CHIC |
| Corrections Issued | 6/3/2019 | ALDOUS CHIC |
| Quality Review Completed | 6/4/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/6/2019 | APPLICANT |
| Applicant returned to address corrections | 6/26/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 12/30/2019 | ALDOUS CHIC |
| Plan Check Approved | 1/17/2020 | ALDOUS CHIC |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 10/21/2022 | EVAN COOPER |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
| CofO Issued | 11/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2019 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 11/15/2019 | ROBERT DUFF |
| Sewer availability | Cleared | 11/15/2019 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 12/17/2019 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 12/24/2019 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 12/24/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2020 | Partial Approval | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 4/10/2020 | No Access for Inspection | EVAN COOPER |
| Special/Order Compliance | 4/10/2020 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 4/15/2020 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 5/18/2020 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 5/19/2020 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/26/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2020 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 6/3/2020 | Partial Approval | MATT KELLERMAN |
| Deputy Wood Construction | 6/12/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 10/22/2020 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/22/2020 | Approved | EVAN COOPER |
| Green Building Rough | 10/22/2020 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 11/9/2020 | Approved | EVAN COOPER |
| HVAC-Rough | 12/1/2020 | Corrections Issued | EVAN COOPER |
| Underground Mechanical | 1/20/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 6/10/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/28/2021 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 6/28/2021 | Approved | EVAN COOPER |
| Green Building Rough | 6/28/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/28/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | EVAN COOPER |
| Gas Test | 8/27/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/27/2021 | Approved | EVAN COOPER |
| Shower Pan | 11/17/2021 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 12/20/2021 | Approved | EVAN COOPER |
| Gas Test | 3/3/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | EVAN COOPER |
| Final | 4/19/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 4/19/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/19/2022 | Approved | EVAN COOPER |
| Structural Steel Frame | 4/19/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/19/2022 | Approved | EVAN COOPER |
| Final | 10/19/2022 | Partial Approval | EVAN COOPER |
| HVAC-Final | 10/19/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 10/19/2022 | Approved | EVAN COOPER |
| Final | 10/20/2022 | OK to Issue CofO | EVAN COOPER |