9009 N HADDON AVE 91352
Certificate Information: 9009 N HADDON AVE 91352
- Application / Permit
- 19014-20000-02533
- Plan Check / Job No.
- B19VN07841
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE 22'-4'x26'-7" TWO STORY ADDITION TO THE REAR (E) ONE STORY SFD WITH ATTACHED GARAGE & ENCLOSE (E)14'X18'7' PATIO COVER TO CREATE (N) DEN
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Green Plans Picked Up | 5/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | DAWN MC NULTY |
| Corrections Issued | 6/4/2019 | DAWN MC NULTY |
| Quality Review Completed | 6/5/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 6/5/2019 | APPLICANT |
| Applicant returned to address corrections | 9/23/2019 | DAWN MC NULTY |
| Plan Check Approved | 11/18/2019 | DAWN MC NULTY |
| Issued | 1/23/2020 | LADBS |
| CofO in Progress | 1/11/2021 | JOHN HAYES |
| Permit Finaled | 2/17/2021 | MICHAEL SMITH |
| CofO Issued | 2/17/2021 | MICHAEL SMITH |
| Permit Finaled | 2/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 7/22/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 7/22/2019 | HERMINIGILDO AGUSTIN |
| Low Impact Development | Cleared | 7/31/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/31/2019 | ELENA LOPEZ |
| Green Code | Cleared | 8/14/2019 | DAVID MATSON |
| Construction near power lines | Cleared | 8/19/2019 | NADER ISKANDER |
| Construction within easement | Cleared | 8/19/2019 | NADER ISKANDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adamian,, Garen; Lic. No.: C74459 | 215 N KENWOOD ST #306 GLENDALE, CA 91206 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2020 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Corrections Issued | JOHN HAYES |
| Deputy Reinf. Concrete | 4/22/2020 | Partial Approval | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 5/4/2020 | Approved | JOHN HAYES |
| Deputy Reinf. Concrete | 5/5/2020 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 5/11/2020 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 5/11/2020 | Partial Approval | JOHN HAYES |
| Deck | 5/18/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | JOHN HAYES |
| Deputy Wood Construction | 6/18/2020 | Conditional Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/2/2020 | Approved | JOHN HAYES |
| Green Building Rough | 7/2/2020 | Approved | JOHN HAYES |
| HVAC-Rough | 7/2/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/2/2020 | Partial Approval | JOHN HAYES |
| MERV13>=Rough | 7/2/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 7/2/2020 | Approved | JOHN HAYES |
| Insulation | 7/10/2020 | Approved | JOHN HAYES |
| Shower Pan | 7/10/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 7/16/2020 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/4/2020 | Approved | BEAU COLLINS |
| Final | 10/22/2020 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/22/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/25/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/25/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/10/2020 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 12/10/2020 | No Access for Inspection | JOHN HAYES |
| MERV13>=Final | 12/10/2020 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/10/2020 | No Access for Inspection | JOHN HAYES |
| Final | 12/14/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 12/14/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 12/14/2020 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/14/2020 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/14/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 12/23/2020 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/8/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 1/8/2021 | Approved | JOHN HAYES |
| MERV13>=Final | 1/8/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/8/2021 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 1/8/2021 | Approved | JOHN HAYES |