16544 W CHATSWORTH ST 91344

Certificate Information: 16544 W CHATSWORTH ST 91344

Application / Permit
19014-20000-02486
Plan Check / Job No.
B19VN07740
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20' X 18' FIRST AND SECOND FLOOR ADDITON TO (E) 20' X 20' GARAGE CONVERTED TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 7/9/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2019 APPLICANT
Green Plans Picked Up 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 ROSENDO MEDINA
Corrections Issued 5/28/2019 ROSENDO MEDINA
Quality Review Completed 5/31/2019 OMID HEDAYAT
Building Plans Picked Up 6/5/2019 APPLICANT
Plan Check Approved 7/9/2019 ROSENDO MEDINA
Issued 7/9/2019 LADBS
CofO in Progress 10/23/2021 MARK JOHNSON
Permit Finaled 12/3/2021 MICHAEL SMITH
CofO Issued 12/3/2021 MICHAEL SMITH
Permit Finaled 12/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/18/2019 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 6/18/2019 SAFA JAVANMARDI
Sewer availability Cleared 6/18/2019 SAFA JAVANMARDI
Low Impact Development Cleared 6/28/2019 ORVAL HERNANDEZ-MARCI
Green Code Cleared 7/1/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 7/1/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 7/1/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 7/1/2019 LEE GUILBEAUX
Hold Cleared 2/25/2021 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/2/2021 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Partial Approval MARK JOHNSON
HVAC-Rough 3/2/2021 Approved MARK JOHNSON
PLUMBING-Rough 3/2/2021 Approved MARK JOHNSON
Underground Mechanical 3/2/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 3/24/2021 Approved MARK JOHNSON
Green Building Rough 3/24/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 3/24/2021 Partial Approval MARK JOHNSON
MERV13>=Rough 3/24/2021 Approved MARK JOHNSON
Sewer 3/24/2021 Approved MARK JOHNSON
Insulation 4/5/2021 Approved MARK JOHNSON
Drywall Nailing 4/12/2021 Approved MARK JOHNSON
Final 8/9/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 8/9/2021 Approved MARK JOHNSON
Green Building Final 8/9/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 8/9/2021 Approved MARK JOHNSON
Final 8/16/2021 Corrections Issued MARK JOHNSON
HVAC-Final 8/16/2021 Approved MARK JOHNSON
PLUMBING-Final 8/16/2021 Approved MARK JOHNSON
Final 9/23/2021 Not Ready for Inspection MARK JOHNSON
Final 10/22/2021 OK to Issue CofO MARK JOHNSON