1255-1257 N STONE ST 90063
Certificate Information: 1255-1257 N STONE ST 90063
- Application / Permit
- 19014-20000-02477
- Plan Check / Job No.
- B19VN07713
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT UNDER (17'10"x30'2" irr.) FLOOR AREA TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. 458SF
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | LUIS RINCON |
| Green Plans Picked Up | 6/13/2019 | APPLICANT |
| Corrections Issued | 6/26/2019 | LUIS RINCON |
| Quality Review Completed | 7/1/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 7/1/2019 | APPLICANT |
| Applicant returned to address corrections | 12/23/2019 | LUIS RINCON |
| Plan Check Approved | 1/24/2020 | LUIS RINCON |
| No Progress | 1/24/2020 | LUIS RINCON |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 3/23/2022 | OSVALDO PARAMO |
| CofO in Progress | 3/23/2022 | OSVALDO PARAMO |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
| CofO Issued | 4/19/2022 | DEROLD HAUFF |
| Permit Finaled | 4/19/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/19/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/19/2019 | ELENA LOPEZ |
| BHO/Hillside ordinance | Cleared | 7/19/2019 | ELENA LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/19/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2019 | JEANIE LAM |
| Sewer availability | Cleared | 8/6/2019 | JEANIE LAM |
| ZI | Cleared | 8/8/2019 | JOE LUCKEY |
| ZI | Cleared | 8/8/2019 | JOE LUCKEY |
| Green Code | Cleared | 10/9/2019 | DAVID MATSON |
| Grading Pre-Inspection | Cleared | 12/23/2019 | LUIS RINCON |
Contact Information
| Contractor | Ivy Green Construction; Lic. No.: 1014647-B | 16800 DEVONSHIRE ST SUITE 222 GRANADA HILLS, CA 91344 |
| Engineer | Ernest, Joseph Bovenizer; Lic. No.: CEG2515 | , |
| Engineer | Haro,, Ruben; Lic. No.: C72213 | 1554 CIPRES CT CAMARILLO, CA 93010 |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 13719 OXNARD ST 101 VAN NUYS, CA 91401 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2020 | No Access for Inspection | OSVALDO PARAMO |
| Piling/Pier/Caisson | 4/17/2020 | Corrections Issued | OSVALDO PARAMO |
| Piling/Pier/Caisson | 4/22/2020 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/24/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/6/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Partial Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/11/2020 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 8/10/2020 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 8/10/2020 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 8/10/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/17/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 8/17/2020 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/21/2020 | Approved | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 8/21/2020 | Approved | OSVALDO PARAMO |
| Insulation | 8/28/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/2/2020 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/4/2021 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 5/28/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/18/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/24/2021 | Approved | OSVALDO PARAMO |
| Final | 8/23/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 8/23/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 8/23/2021 | Approved | OSVALDO PARAMO |
| MERV13>=Final | 8/23/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 8/23/2021 | Approved | OSVALDO PARAMO |
| Final | 3/2/2022 | Corrections Issued | CRAIG DAVIS |
| Final | 3/11/2022 | OK to Issue CofO | OSVALDO PARAMO |