22917 W OXNARD ST 91367

Certificate Information: 22917 W OXNARD ST 91367

Application / Permit
19014-20000-02362
Plan Check / Job No.
B19VN07342
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EXISTING SFD
Permit Issued
Issued on 7/12/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/28/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2019 APPLICANT
Green Plans Picked Up 5/16/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 SAMUEL GONZALEZ
Corrections Issued 5/28/2019 SAMUEL GONZALEZ
Quality Review Completed 5/30/2019 CHON CHIO KUO
Building Plans Picked Up 6/3/2019 APPLICANT
Plan Check Approved 7/3/2019 SAMUEL GONZALEZ
Issued 7/12/2019 LADBS
CofO in Progress 9/3/2020 TROY SANDERS
Permit Finaled 10/28/2020 JOHN JANSON
CofO Issued 10/28/2020 JOHN JANSON
Permit Finaled 10/28/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/10/2019 LEE GUILBEAUX
Sewer availability Cleared 6/10/2019 LEE GUILBEAUX
Green Code Cleared 6/25/2019 MICHAEL AYERS
Low Impact Development Cleared 6/27/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 7/1/2019 APEKSHYA BAJRACHARYA
Grading Pre-Inspection Cleared 7/10/2019 SAMUEL GONZALEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2019 Partial Approval RYAN MCGILL
Pre-Inspection 7/17/2019 Approved RYAN MCGILL
Sewer 7/17/2019 Approved RYAN MCGILL
Underground Mechanical 7/17/2019 Partial Approval RYAN MCGILL
Footing/Foundation/Slab 7/22/2019 Corrections Issued RYAN MCGILL
Structural Steel Frame 7/22/2019 Partial Approval RYAN MCGILL
Deputy Reinf. Concrete 7/23/2019 Approved RYAN MCGILL
Deputy Steel/Welding 7/23/2019 Approved RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Approval RYAN MCGILL
Footing/Foundation/Slab 8/5/2019 Approved RYAN MCGILL
PLUMBING-Rough 8/5/2019 Partial Approval RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 8/13/2019 Partial Approval RYAN MCGILL
Sewer 8/13/2019 Approved RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Corrections Issued RYAN MCGILL
Floor/Roof Diaphrgm/Shear Wall 10/3/2019 Partial Approval RYAN MCGILL
ELECTRICAL-Rough 10/28/2019 Not Ready for Inspection DONALD SUNSERI
PLUMBING-Rough 10/28/2019 Not Ready for Inspection DONALD SUNSERI
Wood Frame 10/28/2019 Not Ready for Inspection DONALD SUNSERI
ELECTRICAL-Rough 11/6/2019 Approved JOHN KIDWELL
PLUMBING-Rough 11/6/2019 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/7/2019 Partial Approval JOHN KIDWELL
HVAC-Rough 11/7/2019 Approved JOHN KIDWELL
Deputy Wood Construction 11/12/2019 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 11/16/2019 Partial Approval DONALD SUNSERI
Green Building Rough 11/16/2019 Not Ready for Inspection DONALD SUNSERI
Interior/Exterior Lathing 11/16/2019 Not Ready for Inspection DONALD SUNSERI
Insulation 11/26/2019 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 12/5/2019 Approved JOHN KIDWELL
Green Building Rough 12/5/2019 Approved JOHN KIDWELL
Insulation 12/5/2019 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/5/2019 Partial Approval JOHN KIDWELL
Drywall Nailing 12/17/2019 Approved JOHN KIDWELL
Shower Pan 12/17/2019 Approved JOHN KIDWELL
Interior/Exterior Lathing 12/31/2019 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 1/29/2020 Partial Approval JOHN KIDWELL
PLUMBING-Rough 1/29/2020 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Final 5/27/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 5/27/2020 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 5/27/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 6/19/2020 Approved TROY SANDERS
Final 6/19/2020 Corrections Issued TROY SANDERS
Green Building Final 6/19/2020 Corrections Issued TROY SANDERS
HVAC-Final 6/19/2020 Corrections Issued TROY SANDERS
PLUMBING-Final 6/19/2020 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Approved TROY SANDERS
Smoke Detectors 6/19/2020 Approved TROY SANDERS
Green Building Final 6/24/2020 Not Ready for Inspection TROY SANDERS
Final 9/3/2020 OK to Issue CofO TROY SANDERS
Green Building Final 9/3/2020 Approved TROY SANDERS
Pre-Inspection 9/11/2020 Approved TROY SANDERS
Special/Order Compliance 10/6/2020 Corrections Issued TROY SANDERS