21903 W YBARRA ROAD 91364
Certificate Information: 21903 W YBARRA ROAD 91364
- Application / Permit
- 19014-20000-02323
- Plan Check / Job No.
- B19VN07265
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel kitchen, doors and windows changeout at living room and bedroom , remove attached patio cover at rear and replaced with 15' x 22'2" addition for new family room per design
- Permit Issued
- Issued on 6/21/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/31/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2019 | ALDOUS CHIC |
| Corrections Issued | 5/3/2019 | ALDOUS CHIC |
| Plan Check Approved | 6/21/2019 | RARES BODEA |
| Plan Check Approved | 6/21/2019 | RARES BODEA |
| Issued | 6/21/2019 | LADBS |
| Permit Finaled | 1/31/2026 | MICHAEL PELHAM |
| CofO Issued | 1/31/2026 | MICHAEL PELHAM |
| Permit Finaled | 1/31/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 5/3/2019 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 6/21/2019 | ALDOUS CHIC |
| Miscellaneous | Cleared | 6/21/2019 | DOMINICK ORTIZ |
| Specific Plan | Cleared | 6/21/2019 | DOMINICK ORTIZ |
| Specific Plan | Cleared | 6/21/2019 | DOMINICK ORTIZ |
| ZI | Cleared | 6/21/2019 | DOMINICK ORTIZ |
| ZI | Cleared | 6/21/2019 | DOMINICK ORTIZ |
Contact Information
| Architect | Stockton,, Richard Kenneth; Lic. No.: C35492 | 20140 ZIMMERMAN PLACE SANTA CLARITA, CA 91390 |
| Contractor | Owner-Builder | , |
| Engineer | Freitas,, Richard Gomes; Lic. No.: C49072 | 240 COPA DE ORO DR BREA, CA 92823 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2020 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 2/27/2020 | Approved | PETER FOLLING |
| BUILDING-Rough-Frame | 3/4/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2020 | Not Ready for Inspection | PETER FOLLING |
| Green Building Rough | 3/4/2020 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Partial Approval | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2020 | Partial Approval | MICHAEL TEMPLE |
| Deputy Drilled-In Anchors | 4/2/2020 | Conditional Approval | MICHAEL TEMPLE |
| Insulation | 4/8/2020 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 4/8/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/10/2020 | Approved | DAVID SANDOVAL |
| Deputy Wood Construction | 4/10/2020 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 4/10/2020 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 4/10/2020 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/16/2020 | Approved | RONALD COWAN |
| Green Building Rough | 4/16/2020 | Approved | RONALD COWAN |
| Insulation | 4/16/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 4/16/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 4/20/2020 | Approved | RONALD COWAN |
| Final | 3/15/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Final | 3/15/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 3/15/2021 | Approved | DAVID SANDOVAL |